Skip to content
FHWA Safety: First graphic from left courtesy of (http://www.pedbikeimages.org/Dan Burden)

Connecticut 2006 Five Percent Report

This report is in response to the Federal requirement that each state describe at least 5 percent of its locations currently exhibiting the most severe highway safety needs, in accordance with Sections 148(c)(1)(D) and 148(g)(3)(A), of Title 23, United States Code.  Each state’s report is to include potential remedies to the hazardous locations identified; estimated costs of the remedies; and impediments to implementation of the remedies other than costs.  The reports included on this Web site represent a variety of methods utilized and various degrees of road coverage.  Therefore, this report cannot be compared with the other reports included on this Web site.

Protection from Discovery and Admission into Evidence—Under 23 U.S.C. 148(g)(4) information collected or compiled for any purpose directly relating to this report shall not be subject to discovery or admitted into evidence in a Federal or State court proceeding or considered for other purposes in any action for damages arising from any occurrence at a location identified or addressed in the reports.

Additional information, including the specific legislative requirements, can be found in the guidance provided by the Federal Highway Administration,
http://safety.fhwa.dot.gov/safetealu/fiveguidance.htm.


CONNECTICUT DEPARTMENT OF TRANSPORTATION
ANNUAL SAFETY REPORT
2005 - 2006

5 Percent Report

Background

SAFETEA-LU created a new Highway Safety Improvement Program (HSIP) as a "core" FHWA program with separate funding, replacing the Hazard Elimination Program, effective October 1, 2005.  The purpose of the HSIP is to reduce traffic fatalities and serious injuries on public roads.  As part of the new HSIP, States are required to submit an Annual Report describing not less than 5 percent of their highway locations exhibiting the most severe safety needs.  The intent of this provision is to raise public awareness of the highway safety needs and challenges in the states.  It is the intention of the FHWA to make each state "5 Percent Report" available to the public on a USDOT Web site.

Procedure Used to Develop the 5 Percent List

Identification and surveillance of locations displaying a higher than expected accidents rate on the highway system are accomplished primarily through a computerized surveillance system (SLOSSS) utilizing traffic record files maintained by the Department's Planning Data and Inventory Section (PDI).  These files consist of:  a crash record file; an average daily traffic file; a roadway characteristic inventory file.  The inventory file identifies locations as being either rural or urban, as either a section of highway, section of expressway, intersection with another state highway, intersection with a town road (or unsignalized drive) or expressway interchange, and further by number of lanes and control of access.  The basic search of the accident file to identify locations that may have an abnormal crash history can take many forms.  In the case of this year's 5 Percent Report, the entire State highway system is surveyed based upon fatal and injury accidents occurring during the latest available period.  A computer program utilizing the previously mentioned data files is run with average accident rates computed.  Based upon these average values, a threshold of abnormally high rates is developed.  Locations with rates equaling or exceeding the threshold value appear on the list.

The list generated for the three year time period covering January 1, 2002 to December 31, 2004 yielded two-hundred ninety eight (298) locations.  The top five percent of these locations are described in sequential order in the table following this narrative.

It is recognized that Connecticut's five percent list considers all reported injuries and does not include local roads.  In accordance with FHWA guidance, it is anticipated that by August 31, 2009, improvements to Connecticut's accident data system will permit future 5 Percent Reports to include local roads and to focus on serious (Type A) injuries.


Highway Segments/Intersections Exhibiting the Most Severe Safety Needs

Location Potential Remedies Estimated Costs Implementation Impediments Comments
Town Route

#1

Woodbridge

Route 243 at Northrop Road and Baldwin Road

Upgrade existing flashing beacon and establish all-way stop control to address the observed angle accident pattern.

$3000

None

This improvement was completed in the field on December 8, 2005.

#2

Enfield

Route 191 at Kressig Road and Abbe Road

Realign side streets and signalize

$150,000

Intersection geometry not conducive to signalization.

Town designing modifications to side street approaches.

#3

Middletown

Route 17 at Main St Extension and Route 9 interchange

Construction of a Single Point Urban Interchange to replace the existing partial free-flow directional interchange.

$55 million

Difficulty maintaining traffic during anticipated staged construction and some local concerns.

The recommended improvement is currently being evaluated as part of State Project #82-279.  This project was initiated in an effort to address existing deficiencies / safety issues and proactively mitigate future problems that may occur along Route 9 and its interchanges in the City of Middletown.

#4

East Haven

Route 100 at US Route 1

Realign Route 100 approach to US Route 1.

$200,000

Impact on business access.

Needs further study.

#5

East Haven

SR 735 at Forbes Place and Kimberly Avenue

Improve intersection control.

$1 million

Insufficient storage to establish desired traffic controls.

Needs further study.

#6

Newington

SR 505 Between CDR S.C. and Holly Drive

Possible roadway widening to construct median island to restrict left turns.

$250,000

Impact on business access.

Needs further study.

#7

New Haven

SR 706 at Route 10

Re-align SR 706 and Route 34 with Route 10.  Upgrade existing traffic control signal.

$2.7 million

Impact to abutting land.

An interim improvement that will revise the lane use and signal operation will be implemented in 2007.

#8

New Britain

Route 71 Between Route 9 ramp & McDonalds

Possible widening to construct median island to restrict left turns.

$250,000

Impact on business access.

Needs further study.

#9

Hamden

Route 10 at Dixwell Avenue

Revise pavement markings to create NB & SB exclusive left turn lanes and 2nd EB left turn lane, create a no parking zone, upgrade signal equipment & revise phasing.

$100,000

None

Project 173-345 will accomplish the recommended improvements.

#10

Meriden

Route 5 Between Town Line Plaza and Broad Street

Signalization and turning lanes.

$400,000

Signalization volume warrants not met.  Geometry not conducive to signalization

Needs further study.

#11

Waterbury

Route 69 Bet Lakewood Road and Shopping Center

Major corridor upgrade including construction of a raised median on Route 69 and roadway widening to provide additional lanes at adjacent signalized intersections.

$1.3 million (2002 dollars) – includes additional work on Route 69 southerly to Frost Road.

Private property acquisitions will be required to implement additional recommended improvements required to address safety concerns and to provide lane continuity within the corridor.

The "Route 69 Traffic Operations Study Final Report" prepared for the Council of Governments of the Central Naugatuck Valley, October 2002, identified the above improvements as a "High Priority".

#12

West Haven

US Route 1 at Brower Street and Route 122

Realign Route 122 with Route 1, widen for exclusive left turn lanes and upgrade traffic signal

$10.83 million

None

Project 156-170 will accomplish the recommended improvements.

#13

New Haven

Route 69 at Pond Lily & Route 15 SB ramp

Widen to provide additional capacity and lane continuity.

$25 million

Impacts to wetlands and abutting properties.

Needs further study.

#14

New Haven

Route 17 at I-91 ramps and Foxon Boulevard

Reconstruct I-91 NB Exit 8 Off Ramp

$14.95 million

None

Project 92-456 will accomplish the recommended improvements.

#15

Enfield

Route 190 Between end of divided highway & beginning of two lanes

Reconstruction of Route 190 at Palomba Drive

$1.9 million

None

Project No. 48-173 was completed 1/25/05.

 

Office of Operations FHWA Safety Home