Skip to content
FHWA Safety: First graphic from left courtesy of (http://www.pedbikeimages.org/Dan Burden)
Home > Five Percent Reports

Minnesota 2007 Five Percent Report

This report is in response to the Federal requirement that each state describe at least 5 percent of its locations currently exhibiting the most severe highway safety needs, in accordance with Sections 148(c)(1)(D) and 148(g)(3)(A), of Title 23, United States Code. Each state's report is to include potential remedies to the hazardous locations identified; estimated costs of the remedies; and impediments to implementation of the remedies other than costs. The reports included on this web site represent a variety of methods utilized and various degrees of road coverage. Therefore, this report cannot be compared with the other reports included on this Web site.

Protection from Discovery and Admission into Evidence—Under 23 U.S.C. 148(g)(4) information collected or compiled for any purpose directly relating to this report shall not be subject to discovery or admitted into evidence in a Federal or State court proceeding or considered for other purposes in any action for damages arising from any occurrence at a location identified or addressed in the reports.

Additional information, including the specific legislative requirements, can be found in the guidance provided by the Federal Highway Administration,
http://safety.fhwa.dot.gov/safetealu/fiveguidance.htm.


Minnesota Annual Highway Safety Improvement Program Report
For State Fiscal Year 2007

E. 5 PERCENT REPORT

Methodology

As a condition for obligating HSIP funds, Section 148©(1)(D) of SAFETEA-LU requires states to prepare an annual report that describes not less than 5 percent of their public road locations exhibiting the most severe safety needs.

For the 2006 HSIP report to the FHWA, Mn/DOT elected to submit a subset of the Top 200 Intersections and Top 150 Sections that represent the highest crash cost locations on the Trunk Highway system in the state. These locations were ranked by crash cost which weighted fatal and serious injury crashes much higher than property damage crashes only, however, the results were generally at locations of high crash incidence and were not based strictly on severe crashes. At the time, we didn't have time or resources to pursue a different ranking procedure.

Since then, we have had the opportunity to see what other states have done with their 5% reports and have decided to make some modifications. The guidance provided by the FHWA suggests utilizing a ranking system based on fatal and serious injury crashes. To that end, we have changed our ranking system.

The capabilities of our data system enable us to produce many reports, but these reports are typically limited to only the Trunk Highway system. Certain elements required to produce reports for all levels of roadway are often simply not present. Both our traditional Top 200 and Top 150 lists are limited in this way.

SECTIONS

Section analysis was previously based only on Trunk Highways, but data indicated that many of the crashes included in our emphasis areas would simply not appear because they occurred on the local system. To solve this issue, and to avoid section breaks at arbitrary increments, we employed a clustering algorithm to report a certain frequency upon a given length. Lane-departure crashes were identified previously as the primary source of our fatal and serious injury crashes. The criteria are as follows:

To compile the list of sections for the top 5% report, the total number of fatal (K) and incapacitating injury (A) lane departure crashes over the last 10 years were tallied (approximately 8300) and 5% of this total was calculated. Lane departure crashes are represented by ran-off-road-left, ran-off-road-right, head-on, sideswipe-opposing, and "other". Through an iteration process, it was determined that sections containing 4 or more crashes (both K and A) per mile most closely represented this 5%. Sections persist beyond one mile so long as the rate of 4 crashes per mile is maintained. These are called "CLUSTERS". Each section's ranking on the 2004-2006 Sections Crash Cost List is shown for comparison. Because the standard Sections Crash Cost List is limited to Trunk Highways only, all county and city sections in this list have no comparable rank. These sections were ranked by the following weight:

[(K*2)+A]/section length

In total there were 554 crashes in 115 clusters which met our criteria. Early analysis shows that 53% of the clusters are in the Metro district, while 54% of the clusters are located on the Trunk Highway system. Seven of the top ten sections are in greater Minnesota.

INTERSECTIONS

Intersections could only be evaluated for Trunk Highways. The list was determined by using a similar methodology as in sections. Over the last 10 years there were approximately 4,800 fatal and serious injury intersection related crashes. 238 Crashes across 26 intersections met or exceeded 5%, of which 46% (12 intersections) are located in the Metro District.

RESPONSES

These lists were distributed to the appropriate jurisdictions in order to determine the following:

  1. Awareness of a potential safety issue
  2. Actions which have been taken during the 10 year time frame
  3. Actions which are anticipated in the near future
  4. Verification of the data. Is there a safety problem?

The table below summarizes these responses. Due to the short time frame, some jurisdictions were unable to respond. Tabular data in this case is marked "no response". Further analysis of these responses will lead to the removal of some of these sections and intersections from the table. It is our intent to update this table on a yearly basis as new data becomes available.

The prime impediments to implementing safety remedies with sufficient impact are funding availability. For the sections list, these costs are significantly higher than the intersections costs, but would undoubtedly have a much greater impact. An additional impediment to implementation is the political acceptability of these improvements. Many of these sections and intersections are in urban areas. Construction projects would have environmental and social impacts which may be unacceptable to local units of government. Another issue for signalized intersections is the debate between safety and capacity in regard to protected left turns. A balance between operations, access and safety will be necessary.

TABLE 9A - Top 5% Sections

Based on 1997-2006 F + A Crashes

RANK TOP 150 RANK SYS NUM COUNTY CITY DISTRICT TOTAL BEG RP END RP Completed projects Construction dates Construction Cost Planned projects Year Planned Cost Notes
K A
1 99 MNTH 65 Anoka   M 3 1 010+00.476 010+00.715 53RD AVE. IN FRIDLEY TO 89TH AVE. IN BLAINE-INTERCONNECTION 1997 $82,582 NONE NONE NONE NONE
AT 85TH AVE.N.E.- REVISE INTERSECTION & SIGNAL 1997 $452,551 NONE NONE NONE NONE
FROM TH 10 TO 45TH AVE. N.E.-SHOULDER BUS LANES 1997 $100,000 NONE NONE NONE NONE
OLD TH10 TO 153RD AVE. NE - MILL & OVERLAY, ETC. 1999 $2,882,122 NONE NONE NONE NONE
85TH AVE. TO 89TH AVE. IN BLAINE-OVERLAY W.FR.RD. 2000 $67,300 NONE NONE NONE NONE
FROM MISSISSIPPI ST. TO BUNKER LAKE BLVD. IN FRIDLEY,SPRING LAKE. PARK, BLAINE AND HAM LAKE.-SIGNING  REPLACEMENT 2005 $151,997 NONE NONE NONE NONE
FROM CSAH 10 TO THE INTERSECTION OF 121ST AVENUE IN THE CITY OF BLAINE - MICROSURFACING 2007 $1,013,268 NONE NONE NONE NONE
2   CSAH 22 Anoka   M 2 2 014+00.196 014+00.426 RESTRIPE ALL COUNTY ROADS ANNUALLY   NONE NONE NONE  
3   CSAH 21 Scott   M 0 7 006+00.626 006+00.972 INSTALLED LEFT AND RIGHT TURN LANES AT EAU CLAIRE/HIGHTLAND INTERSECTION Spring 2007 $14,000,000* RECONSTRUCTION TO A 4-LANE DIVIDED.    $    20,000,000 * PART OF A LARGER PROJECT ON CSAH 82
4   CSAH 16 Ramsey   M 1 3 001+00.400 001+00.650 NONE     NONE     THE COUNTY IS AWARE OF THE CRASHES, NO PROJECTS ARE PLANNED.
5   CSAH 19 Freeborn   6 0 4 000+00.000 000+00.207 NONE     THIS ROUTE IS IN OUR CIP AS THE SECOND STAGE OF A 2 STAGE PROJECT RECONSTRUCTION OF A BRIDGE, DAM, TRAILS, AND ROADWAY. 2009   THIS SEGMENT DID NOT COME UP ON THE COUNTY'S SHORT LIST OF POTENTIAL RSA LOCATIONS.  IT WILL BE ADDED AND STUDIED FURTHER LATER THIS YEAR.
6   CSAH 7 Chisago   M 0 4 007+00.180 007+00.417 CURRENTLY UNDER CONSTRUCTION, 12' LANES, 8'SHOULDER, TURNING AND BYPASS LANES         $3,880,000  
7   CSAH 12 Wright   3 3 3 003+00.111 003+00.700 TOTAL RECONSTRUCTION OF ROADWAY FROM 200 FEET NORTH OF 45TH ST. SW TO ABOUT 1000 FEET NORTH OF 15TH STREET SW - APPROX. 3.3 MILES. THE OLD ROADWAY WAS 2-LANE, 2-WAY BITUMINOUS WITH 2 FOOT AGGREGATE SHOULDERS 2005-06 $3,000,000 FULL RECONSTRUCTION OF THE REST OF THE CORRIDOR (2.3 MILES), FROM THE END OF THE 2005-06 PROJECT TO TH 25 IN THE CITY OF BUFFALO 2010 $2,600,000 THE COUNTY WAS AWARE THAT THERE WAS A CRASH PROBLEM ALONG A CORRIDOR THAT STRETCHED 7.1 MILES.  THEY COMPILED CRASH DATA IN FEB 2003 AND FOUND 50 CRASHES IN A 3 YEAR PERIOD.
THE CITY OF MONTROSE RECONSTRUCTED CSAH 12 FROM TH 12 TO 45TH STREET SW IN 2 PHASES WITH AN URBAN DESIGN 2005          
8 1310 USTH 169 Itasca   1 1 4 300+00.133 300+00.529 REBUILT FROM NARROW 2-LANE ROAD OVER POKEGAMA LAKE TO  LANE SECTION WITH A MEDIAN. CURVES ON EITHER SIDE OF THE CAUSEWAY WERE FLATTENED ALONG WITH BETTER INSLOPES. 2005-06 $7,000,000        
9 273 USTH 61 Houston   6 0 4 000+00.000 000+00.272 NONE     NONE NONE NONE 2 ALCOHOL RELATED & 1 MEDICAL CONDITION CRASH.
10 96 USTH 169 Scott   M 2 2 115+00.833 116+00.345 OVER C.R. 18 AND UP RR-CONSTRUCT RAILING ON BRS. 70523 & 70524 & EXTEND RAILING ON BR 6515(CAYUGA BR) 1999 $138,060 NONE NONE NONE  
AT COUNTY ROAD 18 IN THE CITY OF SHAKOPEE - PARK AND RIDE LOT 2006 $1,617,564 NONE NONE NONE  
SITE PREPARATION TO CONSTRUCT 500 STALL PARK-N-RIDE SURFACE LOT SOUTH OF TH 169, EAST OF CSAH 18 IN THE CITY OF SHAKOPEE 2006 $135,422 NONE NONE NONE  
CONSTRUCT 500 STALL PARK-N-RIDE SURFACE LOT SOUTH OF TH 169, EAST OF CSAH 18 IN THE CITY OF SHAKOPEE 2006 $1,566,630 NONE NONE NONE  
11 2 ISTH 94 Hennepin   M 3 2 232+00.032 232+00.585 CEDAR TO SNELLING AVE-MILL & BITUMINOUS OVERLAY MAINLINE;  CEDAR TO JOHN IRELAND BLVD.-SHLD.REHAB. 2000 $4,146,070 NONE NONE NONE  
12   CSAH 18 Goodhue   6 1 4 004+00.760 005+00.210 NONE NONE NONE NONE NONE NONE  
13 47 USTH 10 Anoka   M 1 3 227+00.116 227+00.504 HANSON BLVD. TO BN RR-MILL & OVERLAY E.B. 1997 $360,144 NONE NONE NONE  
14   CSAH 81 Hennepin   M 0 9 000+00.028 000+00.746 NONE NONE NONE NONE NONE NONE HENNEPIN COUNTY USES ITS OWN CRASH DATA FOR COUNTY ROADS WITHIN MINNEAPOLIS FROM 1998-PRESENT
15 46 ISTH 94 Hennepin   M 2 2 227+00.356 227+00.846 TH694 TO 0.5 MI.N.OF LOWRY TUNNEL-MINOR CONC.REPAIR & RESEAL JOINTS 1998 $1,715,015 NONE NONE NONE  
16 231 ISTH 35 Rice   6 3 3 051+00.476 052+00.222 NONE     CABLE MEDIAN GUARDRAIL INSTALLATION IN PROGRESS. 2007 $550,000  
17 481 ISTH 35 Carlton   1 0 6 231+00.227 231+00.727 DIAMOND GRINDING ON THE BRIDGE AND EITHER SIDE HAS BEEN DONE TO INCREASE FRICTION AND REDUCE WINTER CRASHES. 2007 $25,000 NONE NONE NONE  
18   CSAH 54 Dakota   M 1 4 000+00.863 001+00.363 BITUMINOUS OVERLAY 1997 part of a 7.1 mile project SHOULDER IMPROVEMENTS AND RUMBLE STRIPS ON CURVES TO THE SOUTH OF THIS AREA.  MORE SHOULDER IMPROVEMENTS IN THE LISTED AREA ARE BEING DETERMINED. 2008-09 TBA THIS SEGMENT OF ROADWAY IS A TWO-LANE, UNDIVIDED ROADWAY WITH MANY HORIZONTAL AND VERTICAL CURVES WITH NO SHOULDERS.  SPEEDING IS AN ISSUE THAT CONTRIBUTES TO THE ACCIDENTS. 
19 485 MNTH 3 Rice   6 2 2 006+00.391 006+00.913 NONE NONE NONE CORRIDOR-WIDE SAFETY IMPROVEMENT PROJECT PLANNED. 2008 $360,000  
20   CSAH 33 Carver   M 2 2 004+00.820 005+00.350 NONE NONE NONE NONE     A ROAD SAFETY AUDIT COMPLETED IN 2006 DID NOT IDENTIFY THIS SEGMENT.
21 79 USTH 10 Washington   M 4 0 301+00.212 301+00.920 NONE NONE NONE NONE NONE NONE WEST OF NORELL RD - CURVE WAS RECONSTRUCTED IN 1980
22   MSAS 197 Hennepin MINNEAPOLIS M 0 5 000+00.620 001+00.065 RESTRIPED TO ACCOMMODATE BIDE LANES 2007   NONE NONE NONE THE CITY MONITORS CRASH DATA BASED ON THE NUMBER OF CRASHES CODED TO INDIVIDUAL INTERSECTIONS, NOT SECTIONS.  THEY HAVE PLANS TO LOOK AT SECTIONS IN THE FUTURE.
23 7 ISTH 35W Hennepin   M 4 2 019+00.279 020+00.212 ON I35E ,BURNSVILLE TO EAGAN; I35W,IN MINNEAPOLIS.; I94,BROOKLYN CENTER TO MINNEAPOLIS.; TH 12 IN WAYZATA-DURABLE STRIPING 2004 $1,100,312 FROM 8th SE IN MINNEAPOLIS TO I-694 IN THE CITIES OF ROSEVILLE, NEW BRIGHTON AND ARDEN HILLS - SIGN REPLACEMENT 2007 $575,000  
AT 1ST ST. & AT 2ND ST. IN MINNEAPOLIS-REPLACE LIGHTING SYSTEM 2003 $270,200 FROM I-94 TO INDUSTRIAL BLVD IN THE CITY OF MINNEAPOLIS - SIGN REPLACEMENT 2011 $350,000  
MISSISSIPPI RIVER TO JOHNSON ST. IN MINNEAPOLIS-PAINT BRS.27989,  27994, 27999, 27885, 27990, 27988, 27886, 27985, 27887, 27888, 27889 INCLUDING TRAFFIC CONTROL 2006 $2,452,420 FROM 8TH STREET TO TH 36 IN MINNEAPOLIS AND ROSEVILLE - BUS SHOULDER REHABILITATION 2011 $0  
FROM MISSISSIPPI RIVER BRIDGE 9340 TO STINSON BLVD BRIDGE 27895 IN THE CITY OF MINNEAPOLIS - CONCRETE REHAB, LIGHTING AND GUARDRAIL 2007 $5,607,504 JOHNSON ST. TO NB I 35W CD RD-BUS ONLY RAMP 2049 $750,000  
AT JOHNSON STREET IN THE CITY OF MINNEAPOLIS - PURCHASE OF MATERIALS FOR UPGRADE AND REPLACEMENT OF COMPONENTS ON THE ANTI-ICING UNIT 2007 $72,953        
24   CSAH 42 Dakota   M 0 5 010+00.942 011+00.460 MICROPAVING WESTBOUND LANES 1999 $310,000       THIS SEGMENT'S ALIGNMENT IN AN "S" CURVE.  THERE ARE CURVE WARNING SIGNS AND ADVISORY SPEEDS.  THE COUNTY IS AWARE THAT THERE ARE SPEEDING ISSUES THROUGH THIS AREA, BUT ARE NOT FULLY AWARE OF THE 5 - A INJURY CRASHES.  THE COUNTY IS DEVELOPING A BETTER SEGMENT REVIEW PROCESS FOR THE COUNTY'S ROADWAYS.
BITUMINOUS OVERLAY 2003 $174,000        
CRACK/SEAL COAT 2007 $32,125        
MILL/ BITUMINOUS OVERLAY. 2007 $565,267        
25 223 ISTH 35 Chisago   M 1 3 138+00.950 139+00.476 FROM 0.5 MI N OF N LIMITS WYOMING(MP137) TO 0.5 MI N OF N LIMITS STACY(MP141)-METRO PORTION OF MICROSURFACING CONTRACT, LOW SP 8822-04 1999 $182,603 FOUR LOCATIONS ALONG CORRIDOR: AT CSAH 22 IN WYOMING, CSAH 19 IN STACY, TH 95 IN NORTH BRANCH AND CSAH 10 IN HARRIS - LIGHTING REPLACEMENT 2011 $320,000  
I-35, WYOMING CR22 TO PINE COUNTY LINE - PURCHASE OF MATERIALS AND RENTAL EQUIPMENT FOR BITUMINOUS MILL AND OVERLAY 2006 $26,614 FROM JCT TH 8 TO CHISAGO/PINE COUNTY LINE - REPAIR OF EXISTING CULVERTS AND DRAINAGE STRUCTURES 2011 $301,000  
ON I35W FROM LEXINGTON AVENUE IN LINO LAKES TO N JCT I35/I35E-TMS INSTALLATION 2007 $638,597 THE PRESENT RIDE (SMOOTHNESS) OF THIS SECTION RANGES FROM 2.5 TO 3.3 (2005) PLACING IT IN THE FAIR TO GOOD CATEGORY.  THE PRIMARY ISSUE WITH THIS SECTION IS DETERIORATED TRANSVERSE CRACKS.  IN 1998 THE CRACKS RECEIVED A SURFACE REPAIR WHICH HELPED FOR A SHORT PERIOD.  CONTINUED DETERIORATION OF THESE CRACKS IS CAUSING THE RIDE TO SUFFER. 2013 $15,305,780  
      0.1 MI.S. OF TH 8 TO 1 MILE NORTH OF CTY RD 3 (NORTH METRO BORDER)-MILL AND BITUMINOUS OVERLAY, DRAINAGE, MISC SAFETY UPGRADES 2049 $0  
26   CSAH 32 Ramsey   M 2 2 002+00.385 003+00.029 NONE     NONE     THE COUNTY IS AWARE OF THE CRASHES, NO PROJECTS ARE PLANNED.
27 195 ISTH 35 Rice   6 3 4 058+00.300 059+00.387 NONE     TH 21 INTERCHANGE GEOMETRIC IMPROVEMENT PROJECT PLANNED.      
28   CSAH 88 Dakota   M 4 1 003+00.750 004+00.735 BITUMINOUS OVERLAY 1996 part of a 4.3 mile project       THE COUNTY WAS NOT FULLY AWARE OF THE 4 FATALS.  THE COUNTY IS DEVELOPING A BETTER SEGMENT REVIEW PROCESS FOR THE COUNTY'S ROADWAYS.
29 589 MNTH 47 Anoka   M 1 4 026+00.358 027+00.016 AT CO RD 30/PLEASANT ST. IN ANOKA-TRAFFIC SIGNAL REPLACEMENT, RESTRIPE TH10 TO PLEASANT, ADD LT. TURN LA. AT PLEASANT, MILL & OVERLAY (TH10 TO COOLIDGE & 180 TO CSAH 24) 2005 $1,844,892 FROM TH 10 TO CSAH 22 IN THE COMMUNITIES OF RAMSEY AND BURNS TOWNSHIP - JOINT POWERS AGREEMENT WITH COUNTY FOR REALIGNMENT ANALYSIS, GEOMETRIC LAYOUT, ENVIRONMENTAL DOCUMENTATION, R/W ANALYSIS 2007 $200,000  
      THE PRESENT RIDE (SMOOTHNESS) OF THIS SECTION RANGES FROM 0.5 TO 2.3 (2006) PLACING IT IN THE FAIR TO POOR CATEGORY.  2012 $806,575  
30 441 USTH 212 Carver   M 3 1 140+00.818 141+00.576 FROM MORSE ST IN YOUNG AMERICA TO W JCT TH 101 IN CHANHASSEN-MILL & OVERLAY SEVERAL AREAS 2002 $22,500 DECK REPAIR 2049    
2.2 MILES EAST OF TH 284 TO TH 41 IN THE CITIES OF COLOGNE AND CHASKA - BITUMINOUS MILL AND OVERLAY 2007 $2,268,882 **MN163** FROM COLOGNE TO CO. RD. 147 - RECONSTRUCTION OF ROADWAY 2049 $60,000,000  
31   CSAH 18 Goodhue   6 2 4 000+00.200 001+00.111              
32 627 MNTH 210 Crow Wing   3 3 1 126+00.547 127+00.349 INSTALLED A LEFT TURN LANE AND STREET LIGHTS AT CR 142 (AIRPORT RD) 2007   NONE      
33 185 USTH 12 Hennepin   M 2 6 152+00.811 153+00.933 ON I35E ,BURNSVILLE TO EAGAN; I35W,IN MINNEAPOLIS.; I94,BROOKLYN CENTER TO MINNEAPOLIS.; TH 12 IN WAYZATA-DURABLE STRIPING 2004 $1,100,312 FROM CSAH 6 TO WAYZATA BLVD. IN THE CITY OF ORONO - TURNBACK 2008 $0  
RAMPS AT CARLSON PKWY IN THE CITY OF WAYZATA.  ALSO, FROM BROWN RD TO GLEN MOOR LANE IN THE CITY OF LONG LAKE - PURCHASE MATERIAL & EQUIPMENT FOR BITUMINOUS MILL & OVERLAY 2004 $60,693 FROM WAYZATA BLVD TO I394 IN THE CITY OF MINNETONKA - BITUMINOUS MILL AND OVERLAY.  PURPOSE - TO IMPROVE THE RIDE (SMOOTHNESS), ELIMINATE REGULAR MAINTENANCE PATCHING, RESTORE THE PAVEMENT STRUCTURE, INCREASE REMAINING SERVICE LIFE, AND TO HELP MEET THE 2014 PAVEMENT PERFORMANCE TARGETS.  THIS WILL COMPLETE THE MAJOR CPR WORK DONE IN 2005 THROUGHOUT THE SEGMENT. 2008 $5,112,000  
RAMPS AT CARLSON PKWY IN THE CITY OF WAYZATA.  ALSO, FROM BROWN RD TO GLEN MOOR LANE IN THE CITY OF LONG LAKE - PURCHASE MATERIAL & EQUIPMENT FOR BITUMINOUS MILL & OVERLAY 2006 $10,494 AT CSAH 6 AND WAYZATA BOULEVARD INTERCHANGES - LANDSCAPING 2008 $70,000  
AT CO RD 6 AND AT WAYZATA BLVD-INTERCHANGE CONSTRUCTION, RETAINING WALLS, ETC & 0.2 MI E OF W LIMITS MEDINA TO CSAH 6, REPLACE BR 4643-MILL & OVERLAY IN THE CITIES OF LONG LAKE & ORONO 2007 $35,677,126 UNDER LUCE LINE TRAIL 4.5MI.W.OF TH494-REPLACE BR.4643 - THIS SP IS PART OF SP 2713-83 AND BRIDGE WAS MOVED TO SP 2713-83 2049 $0  
34 5 ISTH 35W Hennepin   M 4 9 015+00.635 017+00.622 ON I35E ,BURNSVILLE TO EAGAN; I35W,IN MINNEAPOLIS.; I94,BROOKLYN CENTER TO MINNEAPOLIS.; TH 12 IN WAYZATA-DURABLE STRIPING 2004 $1,100,312 FROM PORTLAND AVENUE TO WASHINGTON AVENUE IN THE CITY OF MINNEAPOLIS - LIGHTING INSTALLATION 2009 $1,250,000  
ALONG I94 FROM JUST W. OF THE LOWRY HILL TUNNEL E. TO THE RIVER CROSSING.  ALONG I35W FROM JUST N. OF THE RIVER CROSSING (WASHINGTON AVE) S. TO N. OF 46TH ST - PLANNING STUDY TO GENERATE ALTERNATIVES 2007 $740,000 LAKE STREET TO MISSISSIPPI RIVER IN THE CITY OF MINNEAPOLIS - BITUMINOUS MILL AND OVERLAY 2009 $3,970,000  
35 49 ISTH 94 Hennepin   M 3 3 236+00.055 237+00.112 LOWRY HILL TUNNEL-LIGHTING AND MINOR EQUIPMENT 2002 $3,743,712 FROM CEDAR AVE IN MINNEAPOLIS TO KELLOGG BLVD IN ST. PAUL AND ON TH280 FROM I94 TO .2 MILES NORTH OF UNIVERSITY AVE - SURFACING, DRAINAGE, UTILITIES, BUS WORK , CONCRETE REHAB AND SIGN RENEWAL 2008 $10,920,000  
DOWLING AVE. TO I694-N.B. BUS ONLY SHOULDER CONSTRUCTION 2003 $305,484 FROM UNDER CP RAIL TO UNDER I94 NB OFF RAMP IN THE CITY OF MINNEAPOLIS - PAINT 7 BRIDGES; NUMBERS 27821, 27549A, 27819, 27814, 27815, 27817 AND 27818 2009 $2,480,000  
0.4 MI.E. OF CO. LINE TO ST.CROIX RIVER-CONCRETE RETROFIT 2004 $5,014,563 FROM NICOLLET AVENUE TO CEDAR AVENUE IN THE CITY OF MINNEAPOLIS (LOCATED IN THE COMMON SECTION OF I35W AND I94) - BITUMINOUS MILL AND OVERLAY 2009 $2,700,000  
EB ON RAMP OVER LYNDALE IN THE CITY OF MINNEAPOLIS - REPAIR OF CONCRETE SLOPE. 2005 $2,500 LASALLE AVENUE BRIDGE # 27836 IN THE CITY OF MINNEAPOLIS - BRIDGE RE-DECK 2009 $1,000,000  
FROM 49TH AVE TO TH 55 IN MINNEAPOLIS-PURCHASE BITUMINOUS MATERIALS FOR WEDGE PAVING 2005 $28,853 UNDER 42ND AVENUE NORTH (CAMDEN BRIDGE) IN THE CITY OF MINNEAPOLIS - BRIDGE 27549A DECK REPAIR 2010 $400,000  
FROM NICOLLET AVENUE TO JOHN IRELAND BLVD.  INCLUDES CS 6282 FROM HENNEPIN/RAMSEY CTY LINE TO JOHN IRELAND AVE - RENTAL OF MILLING MACHINE FOR PROFILE MILLING 2006 $16,000 MISSISSIPPI RIVER TO MARION ST-TEMP WIDENING,BYPASSES,ETC 2049 $1,185,000  
I94 FROM DUPONT AVE. TO 4TH ST. IN BROOKLYN CENTER & MINNEAPOLIS-BUS SHOULDER 2005 $0 1000 E OF FRANKLIN TO CRETIN ON EB-GR,SU,SIGNING,LT,TM,SIGNALS 2049 $2,935,000  
94 WB RAMPS TO SHINGLE CREEK PKWY, SHINGLE CREEK PKWY RAMP TO 96 WB - PURCHASE OF MATERIALS AND RENTAL EQUIPMENT FOR BITUMINOUS MILL AND OVERLAY 2006 $336,699 SB TH 280 TO WB I94- HOV RAMP METER BYPASS 2049 $1,800,000  
      INSTALL ANTI-ICING DEVICES FOR WESTBOUND I-94 LANES OVER MN 280.  THERE ARE CURRENTLY 20+ CRASHES ON WB I-94 AT THE MN 280 BRIDGES THAT ARE DIRECTLY RELANED TO SNOW AND ICE CONDITIONS.  AN ANTI-ICING SYSTEM SHOULD REDUCE/ELIMINATE THE ICE AND FROST INDUCED CRASHES THAT OCCUR IN THIS AREA. 2049 $700,000  
36 1 ISTH 94 Hennepin   M 5 2 212+00.401 213+00.809 At CSAH 109 (WEAVER LAKE ROAD) - TURN LANES AND SIGNAL MODIFICATION. 1998 $179,901 NONE NONE NONE  
37 585 CSAH 83 Scott   M 2 2 002+00.528 003+00.238 INSTALLED LEFT AND RIGHT TURN LANES AT VALLEY VIEW ROAD Summer 2006 $449,000* EXPANSION TO 4-LANE DIVIDED WITH TURN LANES. Unknown - to be funded by Shakopee Sioux Community Unknown *PLUS SANITARY AND WATERMAIN IMPROVEMENTS
38   ISTH 94 Stearns   3 1 3 157+00.883 158+00.450 MICRO SURFACING ON THE WB RIGHT LANE AFTER THE BRIDGE TO HELP WITH SKID RESISTANCE. 2006 Maintenance NONE NONE NONE THIS AREA IS A HORIZONTAL CURVE ON A BRIDGE AND DOWNGRADE WB AND A DIVERGE POINT FOR TRAFFIC BETWEEN CSAH 75 AND EB I-94 IN THE EB DIRECTION.  MOST OF THE PROBLEM IS ON THE BRIDGE WITH FROST AND SLIPPERY PAVEMENT.
39   CSAH 4 Waseca   7 0 4 017+00.111 017+00.590 NONE NONE NONE NONE NONE NONE WASECA COUNTY IS AWARE OF THE MAGNITUDE OF THE INCIDENTS AT THIS LOCATION.
40 377 ISTH 35 Freeborn   6 1 3 008+00.500 009+00.146 NONE     NONE      
41   CSAH 22 Anoka   M 1 3 020+00.832 021+00.441 RESTRIPE ALL COUNTY ROADS ANNUALLY   NONE NONE NONE  
42 133 ISTH 35W Anoka   M 0 4 041+00.249 041+00.743 ON I35W FROM LEXINGTON AVENUE IN LINO LAKES TO N JCT I35/I35E-TMS INSTALLATION 2007 $638,597 SB 35W AT 35E IN FOREST LAKE - PURCHASE OF MATERIALS AND RENTAL EQUIPMENT FOR BITUMINOUS MILL AND OVERLAY 2008 $89,500  
      FROM I-694 TO I-35 IN FOREST LAKE - SIGNING REPLACEMENT 2009 $1,050,000  
43 619 CSAH 9 Anoka   M 1 3 008+00.618 009+00.236 RECLAIM AND OVERLAY FROM CSAH 22 TO CSAH 24, SIGNING AND STRIPING IMPROVEMENTS, INCREASED PAVEMENT SMOOTHNESS 2002 $305,000 NONE NONE NONE  
44 43 ISTH 94 Hennepin   M 2 4 214+00.565 215+00.579 AT ELM CREEK REST AREA-BLDG. REMODELING-BID BY C.O.BLDG.MAINT.    PROCESS 1999 $624,480 I94 FROM WEAVER LAKE ROAD TO TH 101, I94 FROM ST. PAUL TO WOODBURY, TH 100 FROM I394 TO I94 - RAMP METER INSTALLATIONS 2008 $100,000  
AT WEAVER LAKE RD. IN MAPLE GROVE-EXTEND RAMP & TMS 1999 $880,074 NEAR DUNKIRK LANE IN THE CITY OF MAPLE GROVE - CMS REPLACEMENT 2008 $85,000  
TH 101 TO I494-REPLACE CULVERTS 1999 $95,903 I94 RAMPS TO TH 101 IN ROGERS AND A REST AREA AND WEAVER LAKE ROAD IN MAPLE GROVE - PURCHASE OF MATERIALS AND RENTAL EQUIPMENT FOR BITUMINOUS MILL AND OVERLAY 2008 $153,000  
UNDER 101ST AVE. N. - OVERLAY & REPLACE JOINTS ON BR.27959 2000 $140,069 FROM THE CROW RIVER TO I494 IN THE CITIES OF ROGERS, MAPLE GROVE AND DAYTON - RESURFACING AND REHABILITATION 2010 $10,500,000  
EASTBOUND I-94 TO TH 101 EXIT RAMP AT ROGERS-BITUMINOUS OVERLAY 2001 $25,000 AT TH 101 IN ROGERS - LIGHTING SYSTEM REPLACEMENT 2010 $140,000  
CROW RIVER TO W.JCT. I494-SHOULDER REPLACEMENT 2002 $5,982,778 FROM TH 101 TO WB I94 IN ROGERS - ADD PARALLEL ACCELERATION LANE 2011 $600,000  
IN MEDIAN FROM THE CITY OF ROGERS  TO WEAVER LAKE. RD. IN MAPLE GROVE- INSTALL CABLE SAFETY BARRIER 2004 $253,583 FROM BOTTOM OF SB MN 101 TO EB I94 ENTRANCE RAMP TO I94 EB 3600' EAST IN ROGERS - CONSTRUCT CD LANE.  DUE TO RAPID GROWTH IN THE ROGERS AREA ON BOTH SIDES OF I-94, THE "SB TH 101 TO EB I-94" AND THE "NB TH 101 to EB I-94" TURNING MOVEMENTS HAVE GREATLY INCREASED.  METRO TRAFFIC HAS DETERMINED THAT IN ORDER TO AVOID FUTURE EB I94 MAINLINE BREAKDOWN, THE TWO ABOVE MOVEMENTS SHOULD BE COMBINED VIA A COLLECTOR DISTRIBUTOR (CD) LANE. 2012 $1,500,000  
NEAR ELM CREEK REST AREA IN MAPLE GROVE-INSTALL CHAIN LINK FENCE ON R/W 2004 $30,720        
FROM 95TH IN MAPLE GROVE TO TH 101 IN ROGERS-INCIDENT MANAGEMENT SYSTEM 2004 $1,122,026        
JUST SO. OF TH 101 TO JUST SO. OF CSAH 101 AND 400' NO. OF RICE LAKE BR. TO 400' SO. OF WEAVER LAKE. RD.-DITCH GRADING & MEDIAN BARRIER FENCE 2004 $0        
FROM TH 101 IN ROGERS TO 101ST AVE. IN MAPLE GROVE-PURCHASE MATERIALS & EQUIPMENT FOR BITUMINOUS MILL & OVERLAY 2004 $23,751        
TH 100 FROM CO. RD. 10 TO I694, I-94 FROM WEAVER LAKE. RD. TO I494, & I-394 FROM TH 100 TO I94-FIBER OPTIC CABLE INSTALLATION 2004 $364,970        
ON WEAVER LAKE RD (CSAH 109) FROM I-94 TO VINEWOOD LON IN MAPLE GROVE - RECONSTRUCT AS 6-LANE DIVIDED RDWY WITH ADJACENT PED/BIKE PATH 2006 $2,267,223        
EB RAMP TO WEAVER LAKE ROAD - PURCHASE OF MATERIAL AND RENTAL EQUIPMENT FOR BITUMINOUS MILL AND OVERLAY 2005 $4,160        
SB 101 RAMP TO WB 94 AND SB 101 MAINLINE @ 94 IN THE CITY OF ROGERS - PURCHASE OF MATERIALS FOR BITUMINOUS MILL AND OVERLAY 2006 $26,625        
45   USTH 61 Freeborn   6 1 4 099+00.218 099+00.962 NONE     NONE     3 MOTORCYCLE CRASHES - NOT ENGINEERING RELATED
46   CSAH 22 Hennepin   M 0 8 003+00.385 004+00.394 NONE NONE NONE THIS IS A PROVISIONAL PROJECT IN HENNEPIN COUNTY 2007-2011 CIP 2007-2011   HENNEPIN COUNTY USES ITS OWN CRASH DATA FOR COUNTY ROADS WITHIN MINNEAPOLIS FROM 1998-PRESENT
47 79 USTH 10 Washington   M 3 1 301+00.895 302+00.807 FROM ST. CROIX RIVER TO TH 61-GRADING & SURFACING 1999 $6,823,316 NONE NONE NONE  
ON TH 10 FROM TH 61 TO PRESCOTT - MICROSURFACING 2005 $345,035 NONE NONE NONE  
48 394 ISTH 35 Pine   1 2 2 206+00.210 207+00.000 NONE     NONE     DISTRICT IS LOOKING AT CLEAR ZONE ISSUES IN THIS SECTION.
49 54 USTH 169 Anoka   M 1 3 145+00.746 146+00.403 TH169 OVER MISS.R. IN ANOKA-STAGE 2-REPL.DECK,BR.4380& PERM. APPROACHES, SIGNAL & LIGHTING 1996 $7,722,593 NONE NONE NONE NONE
 MISSISSIPPI RIVER TO TH 10 IN ANOKA-RECONSTRUCT, WIDEN, ETC. 2001 $6,863,883        
50 107 USTH 10 Anoka   M 1 6 230+00.051 231+00.106 FROM EGRET BLVD. TO UNIVERSITY AVE-LANDSCAPING 2000 $264,778 TWO BRIDGES OVER RAILROAD LINE, EB BRIDGE # 09722 AND WB BRIDGE #09721 IN COON RAPIDS - BRIDGE RE-DECK AND GUARDRAIL IMPROVEMENTS.  BRIDGE WAS BUILT IN 1966. WILL BE REPLACED AS A PART OF A PARTNERSHIP PROJECT FOR THE PROPOSED ROADWAY EXPANSION PROJECT. 2008 $2,600,000  
FROM 7TH AVE. TO EGRET AVE. IN COON RAPIDS & BLAINE-PURCHASE AGGREGATE FOR SHOULDERING 2003 $8,616 FROM 1000FT W OF EGRET BLVD TO 1000FT E OF CREEK MEADOWS DR  IN COON RAPIDS - ADD 3RD LANE 2008 $3,000,000  
RAMP TO ROUND LAKE BLVD IN THE CITY OF COON RAPIDS - PURCHASE MATERIAL AND RENTAL EQUIPMENT FOR BITUMINOUS MILL AND OVERLAY 2006 $18,133 AT TH242 IN COON R.-GR,SURF,HOV LN.,SIGS,LTS,SGNS,METER,RECON.BR.02011 2049 $3,000,000  
EB AND WB 10 MAINLINE AT 96, WB 10 MAINLINE AT 35W, EB 10 MAINLINE AT ROUND LAKE BLVD - PURCHASE OF MATERIALS AND RENTAL EQUIPMENT FOR BITUMINOUS MILL AND OVERLAY 2007 $103,644        
51 149 MNTH 100 Hennepin   M 0 5 007+00.649 008+00.317 29TH AVE.NO.TO 39TH AVE.NO.-BR.,FR.RD.& RAMP CONST.,SIGN.,LIGHT.,FENCING (STAGE 2) 2000 $24,781,288 I94 FROM WEAVER LAKE ROAD TO TH 101, I94 FROM ST. PAUL TO WOODBURY, TH 100 FROM I394 TO I94 - RAMP METER INSTALLATIONS 2008 $100,000  
AT I-394 IN GOLDEN VALLEY-MILL & OVERLAY CD LANES 2002 $20,000 FROM WEST 50TH STREET/VERNON AVENUE TO TH 55 IN THE CITIES OF ST. LOUIS PARK, EDINA AND GOLDEN VALLEY - SIGN REPLACEMENT 2010 $450,000  
ON I394 FROM I494  IN MINNETONKA TO PENN AVE. IN MINNEAPOLIS & ON TH 100 FROM BN RR TO GLENWOOD AVE. IN ST. LOUIS PK. AND GOLDEN VALLEY-RESURFACING MAINLINE, CD ROADS, ETC 2004 $5,651,990        
52 1060 USTH 10 Benton   3 2 2 168+00.520 169+00.330 NONE     NONE      
53 294 USTH 169 Sherburne   3 2 3 162+00.822 163+00.779 NONE     NONE      
54   CSAH 152 Hennepin   M 1 5 008+00.360 009+00.334 NONE NONE NONE NONE NONE NONE HENNEPIN COUNTY USES ITS OWN CRASH DATA FOR COUNTY ROADS WITHIN MINNEAPOLIS FROM 1998-PRESENT
55 441 MNTH 47 Anoka   M 2 2 024+00.800 025+00.627 FROM 153RD TO 180TH WAY - M & O ,TURN & BYPASS LANES AND CULV. REPLACEMENT. 2000 $1,437,140 NONE NONE NONE  
56   CSAH 13 Olmsted   6 1 3 000+00.000 000+00.700 PAVEMENT OVERLAY, LANES WIDENED FROM 10 FEET TO 12 FEET. 2005          
57 360 MNTH 5 Carver   M 3 1 033+00.000 033+00.989 AT CSAH 30-INSTALL NEW TRAFFIC SIGNAL SYSTEM  AT W. LEG OF CSAH 30 2006 $380,000 0.2 MI.E. OF TH 284 TO 0.3 MAW. OF T.H. 41-RECONST. 2049 $3,900,000  
58 156 MNTH 3 Dakota   M 2 4 039+00.370 040+00.517 TH 55 TO I-494 - MILL AND OVERLAY 1999 $410,601 THE PRIMARY PURPOSE OF THIS POJRECT IS TO RESURFACE, IMPROVE THE PAVEMENT RIDE (SMOOTHNESS), AND INCREASE THE REMAINING SERVICE LIFE OF THE ROAD PAVEMENT FROM TH 149 to TH 110. REPLACE, REPAIR, OR CLEAN THE EXISTING DETERIORATED CULVERTS, CATCH BASINS, APRONS, CURB AND GUTTER AND TO ALLEVIATE EROSION AND WATER-RELATED PROBLEMS ON THE ROAD AND IN DITCHES FROM TH 149 TO ORME STREET IN WEST ST. PAUL. 2049 $1,911,546  
TH 149 TO TH 55 - MILL & OVERLAY, ETC. 1999 $462,163        
59 35 ISTH 94 Hennepin   M 2 3 207+00.208 208+00.208 CROW RIVER TO CO RD 130 - SIGN REPLACMENT. 1997 $138,409 NONE NONE NONE NONE
60   CSAH 75 Stearns   3 1 3 005+00.111 005+00.834 AN INTERCHANGE, ALONG WITH SOME ROADWAY REALIGNMENTS AT I-94. 2005 $7,737,363 NONE     A REVIEW OF ACCIDENT REPORTS SHOWS SOME CONFLICTING INFORMATION.  THE MAJORITY OF CRASHES REVIEWED HAPPENED BEFORE THE CONSTRUCTION PROJECT.
61 195 MNTH 47 Anoka   M 2 2 025+00.528 026+00.414 FROM 153RD/ALPINE DR. TO CR 22 IN RAMSEY AND BURNS TOWNSHIP-PURCHASE MATERIALS FOR AGGREGATE SHOULDERING 2004 $16,316 NONE NONE NONE  
62 441 ISTH 35 Rice   6 3 3 063+00.340 064+00.653 NONE     NONE      
63 133 ISTH 35W Anoka   M 4 2 036+00.468 037+00.942 TH 118 TO N.JCT. I35E-TH 118 TO 95TH-MILL & BITUMINOUS OVERLAY; 95TH TO N JCT 35E-UNBONDED CONCRETE OVERLAY 1999 $10,217,400 NONE NONE NONE NONE
64 61 MNTH 100 Hennepin   M 1 5 004+00.730 005+00.730 FROM I494 TO EXCELSIOR BLVD.-CONCRETE REHAB.,BUS SHOULDERS (BENTON TO EXCELSIOR BLVD.) NB ONLY 2000 $3,430,310 FROM WEST 50TH STREET/VERNON AVENUE TO TH 55 IN THE CITIES OF ST. LOUIS PARK, EDINA AND GOLDEN VALLEY - SIGN REPLACEMENT 2010 $450,000  
FROM W.41ST.TO 584'N. OF W.41ST.ST. IN ST. LOUIS PARK (EAST SIDE)-NOISE WALL,FR. RD. & CITY UTILITIES 2000 $305,895 36TH ST. TO CEDAR LAKE RD.-INTERCHANGE RECONSTRUCTION, REPLACE BRS 5308,5309,5462 , 5598 & 27012 2014 $118,800,000  
UNDER PED BRS., EDEN ,50TH, MINNEHAHA CREEK,44TH IN EDINA & ST. LOUIS PK.-PAINT BRS. 9895,9896,27029,27102,27103,27104,27105 2005 $1,140,169        
FROM 36TH STREET TO CEDAR LAKE ROAD IN THE CITY OF ST. LOUIS PARK - THIRD LANE ADDITION, INTERCHANGE REVISION, MILL AND OVERLAY AND MISC BRIDGE WORK ON BRS 5308, 5309, 5598, 27012 2006 $7,519,252        
AT BENTON AVE & AT VERNON/50TH ST W IN EDINA; AT EXCELSIOR BLVD IN ST LOUIS PARK-CONCRETE PAVEMENT REPAIR ON VARIOUS RAMPS 2007 $544,938        
65   CSAH 3 Hennepin   M 0 7 012+00.503 013+00.532 ROADWAY RECONSTRUCTION INCLUDING TURN LANES AND CHANNELIZATION     NONE NONE NONE HENNEPIN COUNTY USES ITS OWN CRASH DATA FOR COUNTY ROADS WITHIN MINNEAPOLIS FROM 1998-PRESENT
66   MSAS 430 Hennepin MINNEAPOLIS M 0 5 001+00.373 002+00.122 STREET LIGHTS, SIGNING, SIGNALS UPGRADED, SOME INTERSECTION REALIGNMENTS WITH RDWY RECONSTR 2001-2003   NONE NONE NONE THE CITY MONITORS CRASH DATA BASED ON THE NUMBER OF CRASHES CODED TO INDIVIDUAL INTERSECTIONS, NOT SECTIONS.  THEY HAVE PLANS TO LOOK AT SECTIONS IN THE FUTURE.
67   CSAH 39 Ramsey   M 1 4 000+00.688 001+00.600 NONE     NONE     THE COUNTY IS AWARE OF THE CRASHES, NO PROJECTS ARE PLANNED.
68   CSAH 2 Hennepin   M 1 3 001+00.184 001+00.958 NONE NONE NONE NONE NONE NONE HENNEPIN COUNTY USES ITS OWN CRASH DATA FOR COUNTY ROADS WITHIN MINNEAPOLIS FROM 1998-PRESENT
69   MSAS 121 Stearns ST CLOUD 3 0 5 000+00.402 001+00.178 A MID-BLOCK PEDESTRIAN=ACTIVATED TRAFFIC SIGNAL SYSTEM WAS INSTALLED ON 33RD AVE. NORTH AT THE EMPLOYEE ENTRACE TO THE ELECTROLUX MANUFACTURING PLANT.  HUNDREDS OF EMPLOYEES ACCESS THIS POINT DAILY. 2000 $35,000 NONE     THE CITY WAS AWARE OF THE PEDESTRIAN SAFETY PROBLEM ON THIS ROADWAY.  THIS PROBLEM MANIFESTED AFTER THE RE-STRIPING OF 33RD AVE AS A FOUR LANE FACILITY.  FOUR PEDESTRIANS WERE STRUCK BY MOTORIZED VEHICLES WITHIN A TWO MONTH PERIOD DURING THE WINTER OF 1999.
70 415 USTH 52 Olmsted   6 1 3 064+00.112 064+00.907 NONE     INTERCHANGE, OVERPASS, ACCESS REMOVAL PROJECT NEARLY COMPLETE. 2007 ~$36,000,000  
71 651 MNTH 169 St Louis   1 1 4 372+00.065 373+00.027 NONE     NONE      
72   CSAH 9 Otter Tail   4 1 4 002+00.220 003+00.186 NONE planned           COUNTY WAS AWARE OF ONLY 2 ACCIDENTS, NO INCAPACITATING INJURIES
73   CSAH 2 Redwood   8 1 3 020+00.604 021+00.410 Striping 2007 $800 FROM TH 71 to CSAH 24, GRADING, PAVING AND GUARDRAIL. 2012 $1,400,000 COUNTY WAS AWARE OF THE MAGNITUDE OF THE INCIDENTS AT THIS LOCATION
74   MSAS 363 Hennepin RICHFIELD M 0 4 001+00.257 001+00.902 BUS PULL-OUTS ON LYNDALE AND IMPROVED THE VISIBILITY OF THE CROSSWALKS IN THE AREA. 2004-2005 Developer paid for most of the cost 6300 BLOCK OF LYNDALE WILL BE RECONSTRUCTED, INCLUDES CROSSWALK TREATMENTS AT 63rd STREET AND LYNDALE AVE INTERSECTION AND ELIMINATE ACCESS POINTS NEAR THE INTERSECTION.  CURB LINES WILL BE MOVED IN AND 6 FOOT BIKE LANES WILL BE INCLUDED. 2008 1,400,000* SAFETY $ OF PROJECT MUCH SMALLER
75 298 USTH 61 Wabasha   6 2 2 066+00.571 067+00.553 NONE     CLRS BEING CONSIDERED WITH FUTURE PROJECT.     4 HEAD-ONS. 2 WEATHER-RELATED.
76 104 ISTH 494 Hennepin   M 2 4 023+00.253 024+00.554 3.22KM N. OF TH 55 TO EB I94 - SIGN REPLACEMENT 1997 $76,596 *MN199* I494 FROM I394 TO I94 & I94 FROM CSAH 61 TO CSAH 30, INCLUDING THE I94/494 FISH LAKE INTERCHANGE - RECONSTRUCTION/EXPANSION INCLUDING 13 BRIDGES 2049 $175,900,000  
AT CSAH 9 IN PLYMOUTH-PEDESTRIAN BRIDGE 1999 $35,734        
CONCORD AVE. IN S.ST.PAUL TO 34TH AVE. N.IN BLOOMINGTON-REPLACE "C" & "D" SIGNS 2001 $174,862        
TH 55 IN PLYMOUTH TO W.JCT. I94 IN MAPLE GROVE-BITUMINOUS MILL & OVERLAY 2002 $978,720        
FROM TH 7 TO BASS LAKE. RD. IN MINNETONKA, PLYMOUTH AND MAPLE GROVE-PURCHASE AGGREGATE FOR SHOULDERING 2003 $31,950        
I-94 FROM SHINGLE CREEK TO BROOKLYN BLVD, I-494 FROM TH 55 TO CSAH 10, I-35W FROM I-35E TO TH 13, TH 169 FROM MEDICINE LAKE ROAD TO BASS LAKE RD - CABLE GUARDRAIL INSTALLATION 2006 $930,995        
77   CSAH 10 Washington   M 0 4 004+00.000 004+00.655 ALL-WAY STOP CONDITION WAS IMPLEMENTED TO  ADDRESS LEFT TURN AND RIGHT ANGLE CRASHES AT THE INTERSECTION OF CSAH 10 AND CSAH 19 2000         A REVIEW OF THE CRASH DATA SHOWED NO SPECIFIC PATTERN AS TO WHY THESE CRASHES WERE OCCURRING.  THIS SEGMENT HAS A CRASH RATE WELL BELOW THE TYPICAL CRASH RATE OF 1.0 CRASHES PER MILLION VEHICLE MILES FOR 2-LANE RURAL ROADWAY.
78   MSAS 158 Ramsey ST PAUL M 2 5 000+00.197 001+00.673 KELLOGG BLVD. STREETSCAPE - REVISION OF STREET LIGHTING, SIGNALS, CROSSWALKS, LANES MARKINGS, ETC. 1997-2001 $5,793,000 INSTALL A NEW TRAFFIC SIGNAL SYSTEM ON KELLOGG AT SMITH IN CONJUNCTION WITH THE ROADWAY EXTENSION OF SMITH AVE BEWTEEN KELLOGG AND 5th/6th/MAIN.  THERE IS A BUS PULLOVER PLANNED ALONG THIS NEW PORTION OF SMITH AVENUE. 2007 $225,000  
NEW SKYWAY BRIDGE INSTALLED OVER KELLOGG FROM RIVER CENTRE RAMP TO XCEL CENTER.   unknown REPLACE CONCRETE UNIT PAVERS IN THE KELLOGG AT SEVENTH ST INTERSECTION. 2007 $125,00  
ELIMINATE HILL STREET NEAR MARKET STREET INTERSECTION AND CREATE A PLAZA AREA ON THE SOUTH SIDE OF KELLOGG BY DISTRICT ENERGY AND THE SCIENCE MUSEUM. 2001 $1,984,000        
MILL AND OVERLAY 2" OF BITUMINOUS.  INSTALLED NEW LANE MARKINGS (TAPE).  RECONSTRUCT STAMPED CONCRETE PEDESTRIAN CROSSWALKS AT WABASHA ST. 2004 $396,000        
PEDESTRIAN COUNTDOWN TIMERS INSTALLED AT THE FOLLOWING INTERSECTIONS WITH KELLOGG BLVD:  BROADWAY, JACKSON, ROBERT, RIVERCENTRE PARKING RAMP, WABASHA, WASHINGTON, WEST 7TH ST. 2002-2006 $48,000        
INSTALLED VARIABLE SPEED DISPLAY SIGN ON KELLOGG JUST EAST OF BROADWAY WHERE WB TRAFFIC IS REQUIRED TO REDUCE SPEED FROM 40MPH TO 30MPH.   $12,500        
79   CSAH 16 Scott   M 1 5 008+00.468 009+00.627 WIDENED TO A 4-LANE UNDIVIDED(WITH SOME TURN LANES) FROM YOSEMITE AVE TO GLENDALE RD. NO MAINLINE LEFT TURN LANES WERE CONSTRUCTED AT GLENDALE ROAD. 1998 $2,400,000 INTERSECTION IMPROVEMENTS AT GLENDALE RD SIGNAL (MEDIAN, LEFT TURN LNAES, AND PROTECTED LEFT TURN PHASING) A ROUNDABOUT IS BEING CONSIDERED AS AN ALTERNATIVE SOLUTION AS WELL. 2010 $900,000 COST FOR ROUNDABOUT OPTION NOT KNOWN, COUNTY WAS AWARE OF THE SAFETY ISSUES AT GLENDALE RD, BUT NOT ALONG THE REST OF THE SECTION.
80 408 ISTH 94 Ramsey   M 2 2 238+00.446 239+00.445 SNELLING/PASCAL TO E.B. I94-HOV RAMP METER BYPASS & REMOVE BR. 1998 $2,074,216 FROM CEDAR AVE IN MINNEAPOLIS TO KELLOGG BLVD IN ST. PAUL AND ON TH280 FROM I94 TO .2 MILES NORTH OF UNIVERSITY AVE - SURFACING, DRAINAGE, UTILITIES, BUS WORK , CONCRETE REHAB AND SIGN RENEWAL 1/25/2008 $10,920,000  
CEDAR TO SNELLING AVE-MILL & BITUMINOUS OVERLAY MAINLINE;  CEDAR TO JOHN IRELAND BLVD.-SHLD.REHAB. 2000 $4,146,070 ON EB FROM CRETIN TO WESTERN-GR,SU,LT,TM,SIGNING,SIGNALS 1/1/2049 $7,565,000  
 WB 94 OFF RAMP TO CRETIN AVE AND ON RAMP FROM DALE ST TO EB I94 - PURCHASE OF MATERIALS AND EQUIPMENT RENTAL FOR BITUMINOUS MILL AND OVERLAY 2004 $30,601 CRETIN TO WESTERN ON WB-GR,SU,LT,TM,SIGNING,SIGNALS 1/1/2049 $7,565,000  
FROM HENNEPIN/RAMSEY COUNTY LINE TO RUTH STREET IN ST. PAUL - PURCHASE MATERIALS FOR FENCE REPAIR 2006 $10,281 MISSISSIPPI RIVER TO MARION ST-TEMP WIDENING,BYPASSES,ETC 1/1/2049 $1,185,000  
FROM NICOLLET AVENUE TO JOHN IRELAND BLVD.  INCLUDES CS 6282 FROM HENNEPIN/RAMSEY CTY LINE TO JOHN IRELAND AVE - RENTAL OF MILLING MACHINE FOR PROFILE MILLING 2006 $16,000 UNDER PEDESTRIAN WALKWAY AT GRIGGS-BR 62832(REP BR 9382) 1/1/2049 $220,000  
 94 WB RAMPS TO SHINGLE CREEK PKWY, SHINGLE CREEK PKWY RAMP TO 96 WB - PURCHASE OF MATERIALS AND RENTAL EQUIPMENT FOR BITUMINOUS MILL AND OVERLAY 2006 $33,699        
81 10 ISTH 94 Stearns   3 2 2 154+00.135 155+00.108 NONE NONE NONE MILL AND OVERLAY THAT WILL INSTALL SHOULDER RUMBLE STRIPS.  PROJECT MIGHT INCLUDE A SUPERELEVATION CORRECTION ON A CURVE. 2009    
NONE NONE NONE NEW SIGNING ALONG WITH CENTER MEDIAN CABLE GUARDRAIL. 2009    
82 220 MNTH 65 Hennepin   M 0 5 002+00.052 002+00.900 13TH AVE. NE TO 27TH AVE. NE IN MINNEAPOLIS.-MILL & OVERLAY 1999 $128,942 NONE NONE NONE  
AT THE BROADWAY AVENUE INTERSECTION IN THE CITY OF MINNEAPOLIS - BRIDGE RAILING INSTALLATION  (FY 06 BI SETASIDE) 2006 $100,000 NONE NONE NONE  
83   CSAH 49 Ramsey   M 0 4 001+00.491 002+00.172 AT THE BROADWAY AVENUE INTERSECTION IN THE CITY OF MINNEAPOLIS - BRIDGE RAILING INSTALLATION  (FY 06 BI SETASIDE)     NONE     THE COUNTY IS AWARE OF THE CRASHES, NO PROJECTS ARE PLANNED.
84 4 ISTH 94 Ramsey   M 2 4 242+00.439 243+00.850 WESTERN AVE. TO WHITE BEAR AVE.-STRIPING 1997 $551,906 I94 FROM WEAVER LAKE ROAD TO TH 101, I94 FROM ST. PAUL TO WOODBURY, TH 100 FROM I394 TO I94 - RAMP METER INSTALLATIONS 2008 $100,000  
0.4 MI.E. OF CO. LINE TO ST.CROIX RIVER-CONCRETE RETROFIT 2004 $5,014,563        
TH52 TO 350' E. OF RUTH ST. - CONCRETE ROADWAY REPAIR; REPLACE JOINTS AND MISC. REPAIR ON BRS. 62838 & 62862 2004 $3,012,878        
ON W.B. I94 AT DALE ST. AND AT TH 61 IN ST. PAUL-PURCHASE MATERIALS AND EQUIPMENT RENTAL FOR BITUMINOUS OVERLAY 2004 $15,375        
85 224 MNTH 5 Ramsey   M 1 4 064+00.903 065+00.963 AT RR CROSSING NEAR ALTON STREET IN THE CITY OF ST PAUL - RAILROAD AGREEMENT FOR CROSSING REPAIR 2007 $47,500 AT ALTON STREET IN THE CITY OF ST. PAUL - RAIL CROSSING CANTILEVER AND GATE INSTALLATION AND CROSSING CLOSURE.  PROJECT TO BE DONE VIA AGREEMENT WITH CITY OF ST. PAUL - NO SCHEDULE NEEDED 2010 $262,500  
86   CSAH 32 Ramsey   M 1 3 003+00.010 003+00.911 NONE     NONE     THE COUNTY IS AWARE OF THE CRASHES, NO PROJECTS ARE PLANNED.
87 139 USTH 10 Anoka   M 0 5 219+00.538 220+00.448 ARMSTRONG BLVD TO SUNFISH LAKE BLVD IN RAMSEY, SCOPING STUDY (2004 APPROPRIATIONS ACT-DISCRETIONARY) 2004 $235,105 AT ARMSTRONG BLVD. (CSAH 83) IN THE CITY OF RAMSEY - MILL AND OVERLAY AND SIGNAL REPLACEMENT 2008 $300,000  
JARVIS ST. TO FAIR OAK AVE.-MILL & BITUMINOUS OVERLAY, BUS SHOULDERS. 2006 $3,023,869        
FROM 171ST AVENUE NW IN ELK RIVER TO VERNDALE AVENUE IN THE CITY OF ANOKA - PURCHASE OF MATERIALS FOR SIGN REPLACEMENT 2006 $46,538        
88   CSAH 10 Otter Tail   4 1 3 007+00.535 008+00.460 HIGHWAY AND BRIDGE WERE  CONSTRUCTED TO MEET CURRENT STATE AID STANDARDS. 2002 $627,550      $         627,550 COUNTY WAS AWARE OF ONLY 1 ACCIDENT, ONLY PROPERTY DAMAGE
89   CSAH 34 Ramsey   M 0 4 003+00.455 004+00.196 NONE     NONE     THE COUNTY IS AWARE OF THE CRASHES, NO PROJECTS ARE PLANNED.
90 889 CSAH 116 Anoka   M 0 6 002+00.187 003+00.314 RESTRIPE ALL COUNTY ROADS ANNUALLY   NONE NONE NONE  
91   CSAH 3 Hennepin   M 1 3 013+00.275 014+00.215 ROADWAY RECONSTRUCTION INCLUDING TURN LANES AND CHANNELIZATION. NONE NONE NONE NONE NONE HENNEPIN COUNTY USES ITS OWN CRASH DATA FOR COUNTY ROADS WITHIN MINNEAPOLIS FROM 1998-PRESENT
92   MNTH 60 Wabasha   6 1 3 197+00.941 198+00.880 NONE     NONE     EXTREMELY WINDING SECTION EAST OF ZUMBRO FALLS
93   CSAH 52 Hennepin   M 1 3 011+00.723 012+00.673 NONE NONE NONE NONE NONE NONE HENNEPIN COUNTY USES ITS OWN CRASH DATA FOR COUNTY ROADS WITHIN MINNEAPOLIS FROM 1998-PRESENT
94 354 MNTH 55 Hennepin   M 2 3 167+00.244 168+00.590 .4MI. E. OF CSAH 50 TO 870' E. OF ARROWHEAD DR.-MICRO SURFACING 2003 $562,082 NONE NONE NONE  
FROM DOGWOOD TO GREENFIELD CITY LIMITS-ACCESS CLOSURES & FR.RD. CONSTRUCTION (ACCESS MGMT. $) 2003 $501,120 NONE NONE NONE  
AT GREENFIELD RD. IN THE CITY OF GREENFIELD-INTERSECTION IMPROVEMENTS 2004 $333,268 NONE NONE NONE  
N.SHORE DR. AT CP RR IN GREENFIELD-INSTALL SIGNALS & GATES 2004 $141,047 NONE NONE NONE  
N. SHORE DR. AT CP RR IN GREENFIELD-INSTALL SIGNALS & GATES 2004 $9,600 NONE NONE NONE  
ON NORTH SHORE DRIVE IN THE CITY OF GREENFIELD - GRADING AND SURFACING 2005 $30,000 NONE NONE NONE  
AT THE INTERSECTION OF GREENFIELD ROAD IN THE CITY OF GREENFIELD - LANDSCAPING 2006 $0 NONE NONE NONE  
95 382 USTH 53 St Louis   1 1 3 056+00.081 057+00.034 NONE     NONE      
96 279 MNTH 101 Carver   M 1 3 009+00.761 010+00.721 AT PIONEER TRAIL IN CHANHASSEN-CHANNELIZE AND TRAFFIC SIGNAL INSTALLATION 2005 $726,461 FROM TH 212 TO LYMAN BLVD IN THE CITY OF CHANHASSEN - BITUMINOUS MILL AND OVERLAY 2008 $670,000  
FROM LYMAN BLVD (CSAH 18) TO SCOTT CO LINE - PRELIMINARY DESIGN STUDY - PHASE I (CORRIDOR SCOPING) 2007 $50,000        
97 162 MNTH 47 Hennepin   M 0 6 003+00.935 005+00.092 E.FR.RD. FROM 30TH AVE. TO ST. ANTHONY BLVD. & APPROACH TO BR.27059-GRADE & SURFACE 1997 $569,724 FROM NORTH OF 40TH AVE NE TO N OF CSAH 10 BRIDGE IN COLUMBIA HTS, FRIDLEY, SPRING LAKE PK, COON RAPIDS-BITUMINOUS M/O, RE-DECK BRS. 9725 & 9726, BUS SHOULDERS, ACCELERATION LANES, ETC 2008 $7,090,000  
UNIV.AVE. ST.ANTHONY,OV.SOO LINE &BNRR-TRANSPLANT VEGETATION 1997 $57,360        
27TH AVE TO 35TH AVE NE-RECONSTRUCT ROADWAY & BRIDGE APPROACHES AND REMOVE BR. 5586 1998 $4,109,060        
UNIV.AVE.ST.ANTHONY, OV.SOO LINE &BNRR-LANDSCAPING PROJECT AREA 1999 $136,128        
AT ST. ANTHONY PARKWAY IN MINNEAPOLIS - PURCHASE OF EROSION CONTROL MATERIALS 2007 $5,600        
BNSF@27TH AVE. N.E., MINNEAPOLIS.-INSTALL SIGNALS & GATES 2007 $188,430        
98   MSAS 425 Hennepin MINNEAPOLIS M 0 4 001+00.314 002+00.103 STREET LIGHTS, SIGNING, SIGNALS UPGRADED, SOME INTERSECTION REALIGNMENTS WITH RDWY RECONSTR 1997-2000   NONE NONE NONE THE CITY MONITORS CRASH DATA BASED ON THE NUMBER OF CRASHES CODED TO INDIVIDUAL INTERSECTIONS, NOT SECTIONS.  THEY HAVE PLANS TO LOOK AT SECTIONS IN THE FUTURE.
99 183 ISTH 94 Stearns   3 1 3 176+00.000 177+00.000 INSTALLED CABLE MEDIAN GUARDRAIL. 2006   NONE      
100 195 ISTH 35 Rice   6 1 3 062+00.643 063+00.640 NONE     NONE     THE DISTRICT WAS AWARE OF 1K & 2A
101   CSAH 152 Hennepin   M 0 6 013+00.187 014+00.398 NONE NONE NONE NONE NONE NONE HENNEPIN COUNTY USES ITS OWN CRASH DATA FOR COUNTY ROADS WITHIN MINNEAPOLIS FROM 1998-PRESENT
102 421 ISTH 94 Douglas   4 0 4 099+00.746 100+00.567 NONE NONE NONE Lighting and rumble strips 2009 $50,000  
103 1167 MNTH 197 Beltrami   2 0 4 002+00.809 003+00.634 NEW SIGNAL TIMING PLANS WERE DEVELOPED AND IMPLEMENTED. 2007   THIS SECTION WILL BE RECONSTRUCTED WITH NEW SIGNAL HARDWARE AT THE INTERSECTIONS OF 5TH AND 15TH, RADII WILL BE INCREASED AT THE INTERSECTIONS AND ALL NEW SIGNING AND STRIPING WILL BE INSTALLED 2008   THIS SECTION IS ALSO PART OF AN ACCESS MANAGEMENT STUDY THAT STARTED IN AUGUST 2007 AND WILL BE CONCLUDED IN AUGUST 2008.  IT WILL PROVIDE RECOMMENDATIONS TO ADDRESS GROWTH ISSUES AND INCREASING TRAFFIC LEVELS THROUGH PROPER ACCESS MANAGEMENT PRACTICES AND SAFETY IMPROVEMENTS.
104   MSAS 342 Hennepin MINNEAPOLIS M 0 4 001+00.214 002+00.055 UPGRADED STRIPING TO POLY PRE-FORMED 2005 $11,000 NONE NONE NONE THE CITY MONITORS CRASH DATA BASED ON THE NUMBER OF CRASHES CODED TO INDIVIDUAL INTERSECTIONS, NOT SECTIONS.  THEY HAVE PLANS TO LOOK AT SECTIONS IN THE FUTURE.
105 1240 MNTH 95 Isanti   3 0 4 038+00.073 038+00.923 INSTALLED CENTERLINE LINE AND SHOULDER RUMBLE STRIPS. 2004   NONE      
106   CSAH 40 Carver   M 0 4 000+00.111 001+00.000 NONE     PLANNING IS IN PROCESS IN RESPONSE TO A ROAD SAFETY AUDIT COMPLETED IN 2006. PROJECTS UNDER CONSIDERATION ARE:  REVIEW OF ADVISORY SPEEDS, UPGRADE THE GUARDRAIL ALONG NB CSAH 40, SEASONALLY STREET SWEEP, PAVING INSIDE SHOULDERS ON CURVES 2007/2008 Not determined THE 2006 ROAD SAFETY AUDIT IDENTIFIED THIS LOCATION AS ONE OF THE TOP 11 CONCERNS IN THE COUNTY.
107   CSAH 17 Anoka   M 0 4 013+00.748 014+00.655 RESTRIPE ALL COUNTY ROADS ANNUALLY   NONE NONE NONE  
108   MNTH 55 Hennepin   M 0 4 192+00.397 193+00.324 HIAWATHA AVE. TO W. RIVER PARKWAY IN MINNEAPOLIS-LAKE ST.  STREETSCAPE 2006 $11,502,860 NONE NONE NONE  
109 38 CSAH 23 Hennepin   M 1 5 000+00.240 001+00.864 NONE NONE NONE NONE NONE NONE HENNEPIN COUNTY USES ITS OWN CRASH DATA FOR COUNTY ROADS WITHIN MINNEAPOLIS FROM 1998-PRESENT
110 147 CSAH 30 Hennepin   M 0 4 006+00.060 007+00.000 NONE NONE NONE RECONSTRUCTION AND UPGRADE OF CSAH 30 (FROM CSAH 101 TO DUNKIRK LANE) 2008    
111   ISTH 94 Wright   3 0 4 201+00.262 202+00.211 INSTALLED CABLE MEDIAN GUARDRAIL. 2004   NONE NONE NONE THIS IS IN THE ALBERTVILLE AREA WHERE THERE ARE TWO HORIZONTAL CURVES AND TWO INTERCHANGES.
112 228 USTH 169 Crow Wing   3 0 4 233+00.070 234+00.027 INSTALLED A CENTER LEFT TURN LANE IN GARRISON. 2006          
113   CNTY 249 Houston   6 0 5 001+00.000 002+00.208 NONE     NONE     COUNTY WAS NOT AWARE OF THE MAGNITUDE OF CRASHES AT THIS LOCATION AND WILL FURTHER REVIEW THE CRASH REPORTS AND SITE
114   MSAS 103 St Louis HERMANTOWN 1 0 4 000+00.111 001+00.086 TOTAL RECONSTRUCTION FROM RURAL SECTION TO URBAN SECTION. 2004 $1,400,000 NONE     CITY WAS NOT AWARE OF THE MAGNITUDE OF THE INCIDENTS AT THIS LOCATION
115   CSAH 1 Rice   6 0 4 014+00.131 015+00.111 CHEVRONS INSTALLED. 2006 $2,000 RECONSTRUCT TO WIDEN SHOULDERS, FLATTEN CURVES, ELIMINATE STEEP INSLOPES 2008 $2,000,000  
116   MSAS 145 Stearns ST CLOUD 3 0 5 003+00.015 004+00.265 NONE     RECONSTRUCT THE HIGHWAY 23 INTERCHANGE WITH 10TH AVENUE.  PROJECT INCLUDES GEOMETRIC IMPROVEMENTS (RELOCATION OF THE TH 23 RAMPS) AND SIDEWALK/BICYCLE LANE IMPROVEMENTS.  TRAFFIC SIGNAL IMPROVEMENTS ARE ALSO BEING CONSIDERED. 2009 Approx. $5,000,000  

TABLE 9B - Top 5% of Intersections

Based on 1997-2006 F + A Crashes

RANK TOP 200 RANK SYS NUM RP DESCRIPTION TOTAL ADT CR SR COST DIST COMPLETED PROJECTS CONSTRUCT DATES CONSTRUCT COST PHASED PROJECTS YEAR PLANNED COST NOTES
K A
1 27 USTH 10 177+00.743 ST GERMAINSTMSAS128/ST CLOUD 1 17 28230 0.2 0.7 $532,000 3 NONE NONE NONE NO IMPROVEMENTS.  THIS IS A CHANNELIZED DIVIDED HIGHWAY AND SIGNALIZED INTERSECTION. NO IMPROVEMENTS PLANNED IN 10 YEARS.      
2 1 MNTH 51 007+00.350 CR B CSAH25/ROSEVILLE 1 13 51889 0.1 0.3 $420,000 M NONE NONE NONE SP 6216-116, ON SNELLING FROM ROSELAWN TO EB MN 36 ENTRANCE RAMP - ADD 3RD LANE, TRAFFIC SIGNAL REVISION AT COUNTY RD B AND HAR MAR ENTRANCE, RIGHT TURN LANES ON MINOR LEGS 2008 $2,000,000 BIG FIX - RELOCATE FRONTAGE ROAD ON THE WEST SIDE.  10/2/06 - SIGNAL REBUILD WILL BE LET (ALONG WITH COUNTY ROAD B).  STILL TRYING TO CONVINCE THE CITY OF ROSEVILLE TO MOVE THE SOUTH FRONTAGE ROAD TO LINE UP WITH THE HARMAR ENTRANCE TO CREATE A 4-LEG INTERSECTION, CONVERT THE NORTH & SOUTH FRONTAGE ROADS TO A BACKAGE ROAD THAT ACCESSES THE INTERSECTION. 
3 10 USTH 169 139+00.786 85TH AV NCSAH109/BROOKPARK 2 9 68255 0.0 0.2 $364,000 M NONE NONE NONE SP 2750-57 CONSTRUCT INTERCHANGE - THIS IS PART OF A LARGER PROJECT. (27-681-27, LET DATE 6/14/2010: CSAH 81 FROM N OF TH 100 TO N OF CSAH 10 IN CRYSTAL - RECONSTRUCT TO A 6-LANE DIVIDED RDWY, PED/BIKE PATH) 2010 $52,527,298  
4 16 MNTH 65 004+00.137 37TH AV RESERVOIR BLVD/COL HEIGHTS 3 7 25866 0.1 0.5 $364,000 M SP 0207-73, INSTALLED RAISED MEDIAN BARRIER AND ACCESS MANAGEMENT. (SIGNAL INSTALLED AND TURN LANES ADDED, LET 4/24/1987;SP0207-50; MEDIAN, M/O 27TH AVE TO 37TH AVE NE, LET 7/24/03, SP141-010-74 FORMERLY SP2710-31) 2002 $1,189,138 NONE NONE NONE MINOR INTERSECTION IMPROVEMENTS BY CITY COMPLETED IN 2003.  CLOSE ACCESS FROM RESERVOIR BLVD, ADD NB AND SB RIGHT TURN LANES, AND ADD EB AND WB LEFT TURN LANES.
5 29 USTH 10 222+00.542 SUNFISH LAKE CSAH 57LT MSAS 113 3 7 48439 0.1 0.2 $364,000 M TURN LANE EXTENSIONS COMPLETED WITH M/O, SP0202-80 2006   SP 0205-85, REBUILD SIGNAL 2008 $210,000  
6 96 MNTH 23 205+00.236 25TH AV MSAS 132/STCLOUD 0 12 43656 0.1 0.3 $336,000 3 ADDED A OVERHEAD SIGNAL INDICATION.  THIS INTERSECTION IS SIGNALIZED AND CHANNELIZED.  2003 minor POSSIBLE CITY PROJECT IN TWO YEARS TO INCREASE 25TH AVE CAPACITY.      
7 298 USTH 169 175+00.730 313TH AV CSAH2 RTT 110LT 5 2 21665 0.1 0.4 $336,000 3 CLOSED THE CROSSOVER MEDIAN. 2003   NONE NONE NONE  
8 2 MNTH 15 150+00.400 S JCT TH 232ND STS/ST CLOUD 0 11 46808 0.1 0.3 $308,000 3 CAPACITY ISSUE. ADDED DUAL LEFT TURN LANES. SIGNALIZED INTERSECTION. 2005   NONE NONE NONE  
9 53 MNTH 47 011+00.563 85TH AV CR132LT MSAS129/BLN 1 9 47301 0.1 0.2 $308,000 M SP 0205-82, EXTEND TURN LANE, ADD ACCELERATION LANE AND REVISE SIGNAL. 2004 $184,242 NONE NONE NONE  
SP 0205-783, INTERCONNECT SIGNALS FROM MISSISSIPPI TO 85TH AVENUE 2002          
10 62 MNTH 65 007+00.686 MISSISSIPPISTCSAH6/FRIDLEY 1 9 41510 0.1 0.3 $308,000 M SP 0207-77, SIGNAL REBUILD 2003 $191,443 NONE NONE NONE THE ADDITION OF A THIRD LANE NB AND SB, ALONG WITH AGGRESSIVE ACCESS CONTROL ARE NEEDED.   BIG FIX - REBUILD INTERSECTION BY REMOVING EAST/WEST SPLIT PHASING AND CHANGING THE TWO APPROACH LANES ON THE MINOR LEG TO 1 LEFT
11 301 MNTH 65 008+00.665 73RD AV NE MSAS 307/FRIDLEY 0 11 44559 0.1 0.3 $308,000 M SP 0207-57, REBUILD SIGNAL AND CONVERT MEDIAN SOUTH OF INTERSECTION TO 3/4 1992 $233,630 NONE NONE NONE THERE ARE TWO PROJECTS IN 2049 FOR THIS LOCATION.   MN65, NORTH OF I694 HAS ISSUES AT MANY OF THE INTERSECTIONS.  ANY FIXES THAT COULD BE COMPLETED WOULD HAVE TO INCLUDE MULTIPLE INTERSECTIONS AND ROADWAY SECTIONS.  THIS HAS CAUSED DIFFICULTIES IN DETERMINING SCOPE AND FUNDING FOR THIS LOCATION.  THERE HAS ALSO BEEN DIFFICULTIES IN COORDINATING WITH LOCAL GOVERNMENT AND DEVELOPERS. THE ADDITION OF A THIRD LANE NB AND SB, ALONG WITH AGGRESSIVE ACCESS CONTROL ARE NEEDED.   ADD WB AND EB THROUGH LANES.
12 19 MNTH 65 015+00.420 TH 242 LTCSAH14 RT/BLAINE 2 6 54807 0.0 0.2 $280,000 M NONE NONE NONE SP 0208-123, CONSTRUCT INTERCHANGE, MN 242 IS A TURNBACK IN 2007. 2007-2008 $33,040,585 SP 0208-118 IS A FREEWAY DESIGN, NO LET DATE ASSIGNED
13 36 USTH 63 043+00.264 37TH ST NW CSAH 22/ROCH 3 4 34316 0.1 0.2 $280,000 6 NONE NONE NONE SIGNAL WILL BE CHANGED TO A PROTECTED LEFT. 2008 $15,000  
14 80 USTH 52 096+00.897 N JCT CSAH24/CANNON FALLS 2 6 19827 0.1 0.5 $280,000 6 NONE NONE NONE ENVIRONMENTAL STUDY AND PRELIMINARY INTERCHANGE DESIGN IN PROGRESS   ~ $30,000,000 COST ESTIMATE FOR ENTIRE PROJECT
15 212 USTH 75 245+00.378 60TH AVE CSAH12/CLAY CO 3 4 4151 0.5 2.0 $280,000 4 NONE     ROUNDABOUT PLANNED 2011 $1,000,000  
16 714 USTH 10 024+00.438 TH 32/2 MIE HAWLEY 4 2 12063 0.1 0.6 $280,000 4 INTERCHANGE CONSTRUCTED 2005 $10,000,000 NONE NONE NONE  
17 5 MNTH 15 151+00.561 8TH ST N CSAH4/STCLOUD 0 9 43970 0.1 0.2 $252,000 3       SIGNALIZED INTERSECTION.  NO IMPROVEMENTS PLANNED IN 10 YEARS. NONE NONE  
18 34 MNTH 47 010+00.876 81ST AV MSAS101 RTMSAS339/FRD 0 9 41221 0.1 0.2 $252,000 M SP 0205-89, SIGNAL REBUILD AND EXTEND NB LEFT TURN LANE...LOCAL ADDITIONS WERE EXTEND AND CONSTRUCT DUAL LEFTS ON MN47, EXTEND RTL'S ON MN47, ADD RIGHT TURN LANE TO MINOR LEG 2007 $423,970 NONE NONE NONE  
19 50 USTH 2 108+00.149 TH 89 LT/W OF WILTON 3 3 11132 0.1 0.7 $252,000 2 CONDUCTED AN IN-HOUSE FIELD SAFETY/CRASH HISTORY REVIEW. INSTALLED TWO RED FLASHERS ABOVE EACH OVERSIZED STOP SIGN ON TH 89. 2007   THIS INTERSECTION WILL BE STUDIED IN GREATER DETAIL TO IMPROVE SAFETY AS PART OF A PRE-DESIGN/DESIGN CONTRACT TO DETERMINE ALTERNATIVES TO EVALUATE REALIGNMENT/GRADE SEPARATION OF THE INTERSECTION AND ADJACENT BRIDGES. 2008   LAST FATAL INVOLVED OUT OF TOWN DRIVER MISSING STOP SIGN.
20 54 USTH 169 196+00.151 190TH ST CSAH11 1 7 12249 0.3 1.1 $252,000 3 CORRECT SIGHT DISTANCE ISSUE. STILL HAVING SIGNIFICANT PROBLEMS. 2004 $1,000,000 IN DISCUSSIONS WITH COUNTY FOR POSSIBLE SAFETY IMPROVEMENTS IN 2012.  POSSIBLY CLOSE CROSSOVER, REROUTE CR 11, OFFSET LEFT TURNS     RURAL INTERSECTION ON VERTICAL HILL.  STILL HAVING SIGNIFICANT PROBLEMS.
21 199 MNTH 21 000+00.223 7TH ST CSAH11MSAS104/FRBLT 0 9 21240 0.1 0.5 $252,000 6 CHANGED SIGNAL TO PROTECTED LEFT LAST YEAR 2006 $10,000 NONE NONE NONE  
22 57 MNTH 21 000+00.000 TH 60 CSAH48BHD/FARIBAULT 1 7 24005 0.1 0.4 $252,000 6 CLOSED NEARBY MEDIAN ON TH 60. 2006 NONE NONE NONE NONE CRASHES FROM MEDIAN WERE BEING CODED TO THIS INTERSECTION.
23 90 MNTH 47 007+00.868 57TH AV CR102LT,MSAS 301 RT/ 1 7 44288 0.0 0.2 $252,000 M NONE NONE NONE ADD FREE RIGHT EB TO SB.  ADVANCE SIGNING SB (OVERPASS BEYOND SIGNAL AT 694 MAY MAKE IT HARD TO SEE).   TIE INTERCHANGE IN W/N I694 RAMPS. 2013 $300,000  
24 139 MNTH 65 021+00.714 CROSSTOWN BLVD CSAH 18/HAM LAKE 1 7 35325 0.1 0.3 $252,000 M NONE NONE NONE SP 0208-115, SIGNAL REBUILD 2008 $250,000  
25 222 ISTH 94 230+00.731 TH 55 OLSON MEMORIAL W RAMPS 1 7 38700 0.1 0.2 $252,000 M SP 2751-49, MILL AND OVERLAY 2007   SP 0108-130, REALIGN FRONTAGE ROAD AND ACCESS MANAGEMENT 2008-2009   THIS SIGNAL IS OPERATED BY THE CITY OF MINNEAPOLIS.  MN/DOT CAN ONLY MAKE SUGGESTIONS FOR SIGNAL PHASING/TIMING; IMPLEMENTING THOSE CHANGES IS UP TO THE LOCAL AGENCY.   IMPLEMENTING A "BIG" FIX FOR THIS LOCATION IS HINDERED BY COORDINATION EFFORTS WITH LOCAL AGENCY AND DEVELOPERS.
26 223 USTH 52 086+00.213 TH 57 & CR8/HADER 4 1 16782 0.1 0.4 $252,000 6 NONE NONE NONE ACCELERATION LANES AND TURN LANE LENGTHENING PLANNED.  INTERCHANGE LONG TERM.   $250,000