Example Intersection Safety Implementation Plan

Return to Table 34.

Description of Production Performance Measures

In this table, for each countermeasure listed, one or more performance measures is provided. For each measure, the table lists a corresponding target completion date and actual completion date.

Countermeasure:

Sign and Marking Improvements – State Stop-Controlled Intersections

  • Basic Set of Sign and Marking Improvements
  • Flashing Solar Powered LED Beacons on Advance Intersection Warning Signs and STOP Signs or Flashing Overhead Intersection Beacons
  • Optional Signing and Marking Improvements Based on the Characteristics of the Intersection

    Measure:
    Issue guidelines

    Target Completion Date:
    Issued by 8/1/09

    Actual Completion Date:
    Date issued


    Measure:

    Identify and implement improvements for 1st 400 intersections

    Target Completion Date
    320 intersection improvements implemented by 10/1/10

    Actual Completion Date:
    Actual number improved by 10/1/10


    Measure:

    Identify and implement improvements for 2nd 400 intersections

    Target Completion Date
    640 intersection improvements implemented by 10/1/11

    Actual Completion Date:
    Actual number improved by 10/1/11


    Measure:

    Identify and implement improvements for 3rd 400 intersections

    Target Completion Date
    960 intersection improvements implemented by 10/1/12

    Actual Completion Date:
    Actual number improved by 10/1/12

Countermeasure:

J-Turn Modifications on High-Speed Divided Arterials – State Stop-Controlled Intersections

Measure:
Issue guidelines

Target Completion Date
Issued by 8/1/09

Actual Completion Date:
Date issued


Measure:

Implement J-turn treatments

Target Completion Date
56 new J-turn treatments in place by 7/1/12

Actual Completion Date:
Actual number in place by 7/1/12

Countermeasure:

Basic Set of Sign and Marking Improvements – Local Stop-Controlled Intersections

Measure:
Issue guidelines to locals

Target Completion Date
Issued by 1/1/10

Actual Completion Date:
Date issued


Measure:

Monitor and track system

Target Completion Date
Monitor and tracking system by 7/1/10

Actual Completion Date:
Monitor and tracking system date in place

Countermeasure:

Signal and Sign Improvements – State Signalized Intersections

  • Basic Set of Signal and Sign Improvements
  • Optional Signal and Sign Improvements Based on the Characteristics of the Intersection
  • Change of Permitted and Protected Left-Turn Phase to Protected Only
  • Advance Detection Control Systems

    Measure:
    Issue guidelines

    Target Completion Date:
    Issued by 8/1/09

    Actual Completion Date:
    Date issued


    Measure:

    Identify and implement improvements for 1st 170 intersections

    Target Completion Date:
    135 intersection improvements implemented by 10/1/10

    Actual Completion Date:
    Actual number improved by 10/1/10


    Measure:

    Identify and implement improvements for 2nd 170 intersections

    Target Completion Date:
    270 intersection improvements implemented by 10/1/11

    Actual Completion Date:
    Actual number improved by 10/1/11


    Measure:

    Identify and implement improvements for 3rd 170 intersections

    Target Completion Date:
    395 intersection improvements implemented by 10/1/12

    Actual Completion Date:
    Actual number improved by 10/1/12

Countermeasure:

Signal and Sign Improvements – Local Signalized Intersections

  • Basic Set of Signal and Sign Improvements
  • Change of Permitted and Protected Left-Turn Phase to Protected Only

    Measure:
    Issue guidelines

    Target Completion Date:
    Issued by 1/1/10

    Actual Completion Date:
    Date issued

    Measure:
    Monitor and track system

    Target Completion Date:
    Monitor and tracking system by 7/1/10

    Actual Completion Date:
    Monitor and tracking system date in place

    Measure:
    Implement improvements

    Target Completion Date:
    387 intersections improved by 7/1/12

    Actual Completion Date:
    Number of local signals improved by 7/1/12

Countermeasure:

New or Upgraded Lighting – State Rural Intersections

Measure:
Issue guidelines

Target Completion Date:
Issued by 8/1/09

Actual Completion Date:
Date issued

Measure:
Implement improvements

Target Completion Date:
64 rural intersections lit by 12/1/12

Actual Completion Date:
Actual number lit by 12/1/12

Countermeasure:

High-Friction Surface – State Intersections

Measure:
Issue guidelines

Target Completion Date:
Issued by 8/1/09

Actual Completion Date:
Date issued

Measure:
Implement skid approach treatments

Target Completion Date:
Anti-skid material applied at 53 high speed approaches to intersections by 12/1/12

Actual Completion Date:
Actual number lit by 12/1/12

Countermeasure:

Enforcement-Assisted Lights

Measure:
Finalize selection of pilot city

Target Completion Date:
4/1/10

Actual Completion Date:
Date finalized

Measure:
Implement red-light enforcement light demo in pilot city

Target Completion Date:
1/1/11

Actual Completion Date:
Date implemented

Countermeasure:

Corridor 3E Improvements on High-Speed Arterials with Very High Frequencies of Severe Intersection Crashes

Measure:
Finalize selection of three corridors

Target Completion Date:
8/1/09

Actual Completion Date:
Actual date

Measure:
Prepare corridor safety countermeasures

Target Completion Date:
11/1/10

Actual Completion Date:
Actual date

Measure:
Implement corridor improvements

Target Completion Date:
12/1/11

Actual Completion Date:
Actual date

Countermeasure:

Municipal-Wide 3E Improvements in Municipalities with High Frequencies of Severe Intersection Crashes

Measure:
Finalize selection of candidate city

Target Completion Date:
12/1/09

Actual Completion Date:
Actual date


Measure:

Prepare set of city countermeasures

Target Completion Date:
Completed by 12/1/10

Actual Completion Date:
Actual date

Measure:
Implement set of countermeasures

Target Completion Date:
Implementation completed by 1/1/12

Actual Completion Date:
N/A

Countermeasure:

Roundabouts

Measure:
Finalize guidelines for roundabout consideration

Target Completion Date:
Completed and issued by 9/1/09

Actual Completion Date:
Actual date issued

Measure:
Complete evaluations of 34 intersections

Target Completion Date:
Completed by 2/1/10

Actual Completion Date:
Date evaluations completed

Measure:
Make decision on roundabouts

Target Completion Date:
7/1/10

Actual Completion Date:
Date decisions made

Measure:
Approved roundabouts in place

Target Completion Date:
In place by 7/1/13

Actual Completion Date:
Date roundabouts functional