Slide 1

Welcome!!
Safe and Effective Use of Law Enforcement Personnel in Work Zones

Session Title:
Module 0. Introduction to course

Performance-Based Learning Outcomes:
Opening module, logistics and other preliminary information.

Instructional Method: Lecture

Session Time: 23 Slides. Approximately 20-25 minutes depending on number of students.

Evaluation Plan:
The learning outcomes are evaluated at the end of each module using the questions contained in the last Slide of that module and through the exercises.

Two-instructor option:
Instructor 1 opens the course; Instructor 2 facilitates student introductions and housekeeping. Instructors may alternate teaching modules as agreed.

Slide 2

Instructor

Key Message: Instructor's self introduction
Est. Presentation Time: Less than 20 seconds
Explanation of Cues/Builds: None
Suggested Comments: This is not your introduction. This is just to mention your name.
Suggested Questions: None
Additional Information: May ask students to write the name down for thecourse evaluations.
Possible Problems: You will establish credibility later. Avoid talking about yourself at this point.

Slide 3

Did you know?
..More police officers are killed by traffic than by bullets
..We have more than 42,000 traffic fatalities every year nationwide
..More than 1,200 of those occur in work zones
..4 times more officers were killed when struck by vehicles than in accidental shootings over the last 10 years
Source: www.nhtsa.dot.gov, www.fbi.gov

Key Message: Describe/quantify the problem of LEO safety when working in highway work zones.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: 4 boxes that appear one at a time when hitting the space bar or remote advance button.
Suggested Comments: Intended to serve as an eye-opener.
Suggested Questions: You may turn each of these boxes into questions before each box appears.
Additional Information: Refer students to www.nhtsa.dot.gov (National Highway Traffic Safety Administration) and www.fbi.gov (Federal Bureau of Investigations) for additional statistics.
Possible Problems: None

Slide 4

Introductions
..Name
..Agency
..City and State
..Experiences and anecdotes with work zones

Key Message: Students' self-introductions
Est. Presentation Time: 10 minutes more or less, depending on class size
Explanation of Cues/Builds: None
Suggested Comments: Inquire about experiences related to work zones. Identify which agencies are represented and what kind of formal training, if any, they have. Ask them why they are there.
Suggested Questions: Why are you here? {Maybe, Does anyone have previous formal training in work zone safety?}
Additional Information: Interject your own experiences as appropriate.
Possible Problems: Some students may take too long by rambling. Keepmoving and, if appropriate, indicate that the material will be covered later. Resist the temptation to discuss items that will be covered later in the class. Keep this moving!

Slide 5

About the Instructor

Key Message: Instructor's self-introduction
Est. Presentation Time: 1 minute or less
Explanation of Cues/Builds: None
Suggested Comments: Purpose of Slide is to establish credibility. Mention your experience with the subject matter and {the length of?} your working experience. Be brief and avoid bragging. Be friendly to develop rapport with students. Keep this brief.
Suggested Questions: None
Additional Information: Try to tie your personal experiences to the experiences expressed by the students.
Possible Problems: None

Slide 6

Logistics
..Ending time
..Restrooms
..Emergency exits
..Breaks
..No smoking
..Cell phones/radios SILENT

Key Message: Course logistics and housekeeping
Est. Presentation Time: 1 minute or less
Explanation of Cues/Builds: None
Suggested Comments: Indicate clearly at what time the class will end and when you intend to take breaks. A ten-minute break every hour is recommended. Keep breaks to the specified duration. {Snack machines or cafeteria or served refreshments? Lunch?}
Suggested Questions: None
Additional Information: None
Possible Problems: Police officers may be reluctant to turn radios off. Indicate they can be in the SILENT mode instead. [cell phones on vibrate?]

Slide 7

How dangerous can WZ be for Law Enforcement Officers?
Picture of tractor-semi-trailer collided with the police vehicle, killing an officer and injuring others.

Key Message: Describe how the lack of training/knowledge can lead to crashes, injuries and/or fatalities.
Est. Presentation Time: 1 minute or less
Explanation of Cues/Builds: None
Suggested Comments: This crash occurred in Jackson, TN. Avoid, however, mentioning that fact. The following Slides illustrate what happened. A slow-moving highway patrol vehicle was impacted by a tractor-semi-trailer (18-wheeler) resulting in the death of the officer and other injuries.
Suggested Questions: None
Additional Information: None
Possible Problems: Officers in class may be familiar with this crash and may take this personally. Avoid assessing blame. The purpose is to illustrate what can happen, not to assess blame.

Slide 8

Diagram of 2 Highway patrol vehicles 500' apart blocking the right lane, with emergency lights operational. The patrol cars are 450' behind construction vehicles involved in a moving milling operation.

Key Message: Illustrate the position of vehicles affected.
Est. Presentation Time: 1 minute or less
Explanation of Cues/Builds: None
Suggested Comments: This was a moving milling operation on a freeway shoulder. All work was on the shoulder. Two highway patrol vehicles were slowly moving on the right lane, basically to serve as a lateral buffer and force freeway traffic to slow down.
Suggested Questions: Do you think this setup is proper? Why or why not?
Additional Information: None
Possible Problems: May have to define "milling operation" and "moving operation". At this point, simply indicate that the operation was continuously moving on the shoulder.

Slide 9

Picture of accident

Key Message: Arrow shows the location of the impact.
Est. Presentation Time: Less than 1 minute.
Explanation of Cues/Builds: The arrow depicts where the initial impact occurred.
Suggested Comments: At about 8:52 a.m., an eastbound tractor semi-trailer traveling at a driver-estimated speed of 65 mph collided with the trailing Highway Patrol vehicle. [Indicate that this is a high-speed facility.]
Suggested Questions: What was wrong with this setup? What did it assume?
Additional Information: The setup assumed that motorists would see the patrol vehicle, recognize that it was moving slowly, and react by switching lanes, all while moving at high speed.
Possible Problems: None

Slide 10

Picture of the patrol vehicle after impact

Key Message: Picture shows the condition of the patrol vehicle after impact.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: The patrol car exploded and caught fire upon impact and was pushed approximately 192 feet before it came to rest in the median. The State trooper in the vehicle was killed.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 11

Picture of tractor-trailer

Key Message: Picture shows where tractor-trailer ended up, after crossing the median and impacting vehicles in the opposite direction.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: The tractor-semi-trailer continued through a 61-foot depressed earthen median and into the westbound lanes, where it collided with a 1997 Chevrolet Blazer. The Chevrolet driver was seriously injured.
Suggested Questions: None
Additional Information: None
Possible Problems:

Slide 12

Picture of road and skid marks

Key Message: Picture shows location of impact
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: None
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 13

Common Pitfalls When Using Law Enforcement Officers in WZ
1. Lack of communication between work zone (WZ) participants
2. Lack of planning and coordination of traffic control responsibilities
3. Inadequate training of law enforcement personnel (LEO) in traffic control procedures within highway work zones

Key Message: Describe some pitfalls that led to this crash
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: During the crash investigation, the following highway and training issues were identified:
• The lack of communication between the state Department of Transportation (DOT), its contractors, and the State Highway Patrol.
• The lack of planning and coordination of traffic control responsibilities between the contractors and the State Highway Patrol before engaging in work zone activities.
• Inadequate training provided to the State Highway Patrol officers on safe traffic control procedures within highway work zones.
Suggested Questions: What do you think led to this crash? Could this crash be avoided? How?
Additional Information: Prior to milling the rumble strips on the day of the accident, the construction foreman advised the LEO that traffic control would be conducted using a "mobile lane closure."
• It was the intent of the foreman to keep all the interstate lanes open, and to have the LEO warn motorists away from the construction vehicles on the shoulder of the roadway.
• The LEO, who again were not trained in work zone traffic control procedures and terminology, did not ask for clarification regarding the traffic control strategy, and proceeded to position their vehicles behind the protection vehicle and in the travel lanes.
Possible Problems: None

Slide 14

Inadequate Training
..May result in officers positioning their vehicles in unsafe locations
..May lead to crashes and injuries

Key Message: Illustrate the importance of training for LEOs working in work zones
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Training is important! Proper training of the LEO may have avoided this crash!
Suggested Questions: Do you think that proper training could have avoided this crash? How?
Additional Information: None
Possible Problems: None

Slide 15

US Government Survey of 46 States
66% Use police officers for work zone projects
20% Provide only general traffic management training

Key Message: Illustrate that even though several states are using LEO in work zones, few are providing training to those officers.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: (click) 66% side appears, (click) 20% side appears.
Suggested Comments: None
Suggested Questions: None
Additional Information: According to a 2001 FHWA/AASHTO report, of the 46 states surveyed, two-thirds use uniformed police officers for federally funded highway construction projects-but only a quarter had a program in place or under development to train those officers working in construction projects.
AASHTO is the American Association of State Highway and Transportation
Officials. FHWA is the Federal Highway Administration.
Possible Problems: None

Slide 16

Why Are Work Zones a Concern?
..Speeding
..Hazards present
..Exposed workers
..Situations not familiar to drivers
..Others?
It is dangerous work!

Key Message: Indicate why work zones are dangerous to all involved
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: Each bullet appears with a click.
Suggested Comments: Indicate that work zones are dangerous to everyone involved, including LEO.
Suggested Questions: Before clicking, you may ask: Why are work zones a concern? Ask if they can think of any other reasons.
Additional Information: None
Possible Problems: None

Slide 17

So, Why Are We Here?
These are our course objectives
..To provide you with working knowledge of traffic control work zones
..To define your roles and responsibilities when working in work zone

Key Message: Discuss course objectives.
Est. Presentation Time: 1-2 min.
Explanation of Cues/Builds: None
Suggested Comments: The primary learning objectives for this course are listed on the Slide.
Suggested Questions: Why are you here?
Additional Information: Try to generate class participation by asking what the students' expectations are. Generate a list of expectations to be discussed at the end of the course.
Possible Problems: Students may not have any expectations. Be prepared to suggest a couple of expectations, such as "To determine where to position my patrol car" or "To find out what equipment I should have with me", etc.

Slide 18

This Training Course
..Provides the basic knowledge that can save lives, including your own, when wworking in a work zone. This knowledge will help you avoid work zone crashes and improve safety!

Key Message: Summarize in simple terms the objectives of the course.
Est. Presentation Time: Less than 1 minute.
Explanation of Cues/Builds: (click) Bottom box zooms in.
Suggested Comments: Consider this a summary Slide.
Suggested Questions: What would this knowledge help you do?
Additional Information: None
Possible Problems: None

Slide 19

On completion, participants will be able to:
1. Understand standards and guidelines related to temporary traffic control in work zones
2. Understand the role of law enforcement officers in work zones
3. Recognize the component parts of a typical work zone
4. Recognize proper practices and procedures related to the use of law enforcement officers in work zones

Key Message: List the things that participants will be able to do after completing the course.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 20

Course Modules = 4 HOURS
1. 30 min. Roles and Responsibilities
2. 60 min. Understanding Work Zones
3. 30 min. Recommended Practices
4. 30 min. Application Workshop
5. 10 min. Closing

Key Message: Describe the modular approach of this course.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: (click) "4 HOURS" zooms in.
Suggested Comments: Tie the duration to the ending time for the course.
Indicate times are approximate and subject to change depending on class composition and interests.
Suggested Questions: None
Additional Information: Encourage class participation.
Possible Problems: Someone may point out that times do not add up to 4 hours. Difference is due to breaks, which are not included.

Slide 21
Course Materials
..Course notebook
..Name tag
..Pencil
..MUTCD can be found on FHWA's website: http://mutcd.fhwa.dot.gov

Key Message: Introduce the course materials.
Est. Presentation Time: Less than 1 minute.
Explanation of Cues/Builds: None
Suggested Comments: None
Suggested Questions: None
Additional Information: Instructor can secure copies of Part VI of the MUTCD if possible, or direct participants to the MUTCD website listed where the manual can be downloaded. All materials are theirs to keep. Encourage students to wear their name tags, which show first names only and are printed in large type. In addition, FHWA will post the Pocket Guide that accompanies this course on their website mid-2005.
Possible Problems: Avoid discussing what the MUTCD is at this point. This will be discussed later.

Slide 22

Safety is an Integral Part of WZs
..Workers
..Motorists
..Pedestrians
..Bicyclists
..LEOs if present

Key Message: Module summary Slide.
Est. Presentation Time: Less than 1 minute.
Explanation of Cues/Builds: (click) for each bullet in box.
Suggested Comments: Emphasize pedestrians and bicyclists: ALL involved!
Suggested Questions: None
Additional Information: Source: www.officer.com
Possible Problems: Not intended to be read, but to illustrate the importance of work zone safety for everyone involved.

Slide 23

Module Recap
..Why are we here?
..How dangerous are WZs for Law Enforcement Officers?
..How big is this problem?

Key Message: Recaps Module 1.
Est. Presentation Time: 2-3 minutes
Explanation of Cues/Builds: None
Suggested Comments: None
Suggested Questions: Ask questions to gauge understanding and summarize the concepts learned. The questions listed are samples. Add questions as needed, addressing the material covered. Try to let students answer the questions before giving the answers.
Additional Information: None
Possible Problems: Students may not understand what we are trying to do. Be prepared to answer these questions yourself, at least for this first module. This is repeated for each of the remaining modules.

Slide 24

Roles and Responsibilities
Session Title: Module 1. Roles and Responsibilities
Performance-Based Learning Outcomes: Understand the roles and responsibilities of everyone involved with highway work zones.
Instructional Method: Lecture
Session Time: 37 Slides. Approximately 30-45 minutes depending on class participation.
Evaluation Plan: Evaluate the learning outcomes at the end of each module by using the questions contained in the last Slide of that module and through the exercises.

Slide 25

Module Objectives
..Recognize the roles of LEOs and others in work zones
..List LEO responsibilities and expectations in work zones
..Discuss communication channels among all involved and the importance of good communication

Key Message: List module objectives
Est. Presentation Time: Less than 1/2 minute
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 26

Decision-Makers
..Set a procedure for how LEOs may be used
..Implement policies
..Be active and engaged - even if contractor is mainly responsible for hiring LEOs
..One state: Regional WZ enforcement coordinators

Key Message: Decision makers within a highway agency should actively promote sound practices and policies for
LEOs in highway work zones.
Est. Presentation Time: 2-3 minutes
Explanation of Cues/Builds: None
Suggested Comments: Example: Oregon Funding -Originally a result of the OR legislature requiring the DOT to invest $1 million of FHWA construction money for special work zone patrols by state police. Now elective decision to continue that investment. The program at a statewide level, rather than on an individual project basis. Program structure -There is a statewide program manager housed in the Governor's Highway Safety Rep office. The
program is implemented on a local basis. Oregon is divided into five Regions. Each Region has delegated a person to
be responsible for the management of a biennial budget of overtime work zone enforcement hours allocated by the
Statewide Program Manager (SPM). Planning -About six months prior to the beginning of a new biennium, the Region Reps, state and local police, project managers and the SPM meet to plan the upcoming biennium's work zone enforcement program. The SPM has armed the Region Reps with a starting budget of hours. The Reps pair that information with the projects in the STIP [Statewide Transportation Improvement Program]. The agenda consists of discussion of program management issues and refinement of the distribution of hours. Program management -The DOT is the "owner" of the program. Region Reps and DOT project managers manage the budget of hours. Although the budget for WZ enforcement is not in the individual project, PMs have been given a project budget. They have control over the use of those hours and petition the Region Rep for additional hours if needed. Region Reps can, in turn, petition the SPM for additional hours if needed and the SPM consults with other Region Reps to see if there are hours to spare. Results - The program was fully implemented in the 1995-97 biennium. 1997 saw a peak in WZ traffic deaths at 21. From that time forward, the deaths declined steadily to a low of two in 2003. Strong DOT-contractor-enforcement partnerships, fairly substantial investments in public education (Give 'Em A Brake) and a strong "double-fine" law are credited with the dramatic improvement.
Suggested Questions: What about your state?
Additional Information: None
Possible Problems: None

Slide 27

Discussion
..Does your state have a defined process for using officers in work zones?
..How is coordination achieved?
..How would you evaluate your current practice?
..Is the process working as well as it could be?

Key Message: Discuss state processes for using LEOs in work zones, if any.
Est. Presentation Time: Depends on length of discussion. Limit to 7 minutes.
Explanation of Cues/Builds: The picture originally had a caption on it titled
"The winner of the 'Not My Job' Award". The picture is meant to introduce
humor and show that coordination and communication is important - even
though traffic control setup may not be a primary function of law
enforcement, when they see improper practices they should bring it to the
attention of the point of contact.
Suggested Comments: Self-explanatory but be prepared to give examples.
Refer to Oregon example, if needed.
Suggested Questions: What problems do you see in your state? How can
this process be improved?
Additional Information: None
Possible Problems: Lack of participation. Be prepared to lead the
discussion.

Slide 28

Typical WZ Stakeholders
1. Highway Agency
2. Contractor
3. Contractor's Point of Contact
4. Traffic control technicians

Key Message: Lists stakeholders in highway work zone implementation,
and shows that the highway agency may coordinate with LEOs, or
contractors may hire LEOs directly to perform work. Even though
contractor may be responsible, the highway agency has a vested interest in
ensuring the safety and efficiency of the operation.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: "LEO" zooms in at click, to illustrate where
LEOs fit in the "chain". Second LEO appears on second click.
Suggested Comments: Do not explain each of the stakeholders at this point.
The following Slides explain each stakeholder in detail. Do not refer to this
as a "chain of command".
Suggested Questions: "Can you think of any other stakeholders?" Someone
may say "the traveling public". Respond by saying that the stakeholders
referred to here are "workers", but that the traveling public is also a
stakeholder.
Additional Information: None
Possible Problems: None

Slide 29

1. Highway Agency
..May be:
..State DOT
..Other local agency
..Responsible for the overall project, including enforcement of the TCP
..The "final authority"
..May contract-out these responsibilities
..Approves a Traffic Control Plan (TCP) for the project

Key Message: Explain the "highway agency" as a stakeholder in highway work zones.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: Text box appears on click. Define a TCP as a
set of drawings that specify how traffic will be controlled during the project.
Emphasize that work zones are carefully planned and executed, and that
LEOs are a part of this plan.
Suggested Comments: Add that the "agency" may be a county, a state DOT
or a city, whoever owns the facility and is responsible for it. Add that the
"agency" may not contract with LEOs directly, but through contractors.
Suggested Questions: Who is the highway agency here? It depends on the
location and magnitude of the project. Most "major" facilities (interstates,
major highways) are owned and maintained by the state.
Additional Information: DOT stands for "Department of Transportation".
Possible Problems: None

Slide 30

1. Highway Agency (cont.)
..May allocate enforcement resources
..May provide inspection services and liaison with LEOs
..Builds the TCP which includes:
..Pattern of TCPs
..Tasks to be performed
..Project phasing

Key Message: Continuation of discussion of TCP.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Emphasize that a TCP is very specific, with nothing
left to chance. A good TCP would specify the location of a LEO, if used.
Suggested Questions: Have you ever seen a TCP? Were you aware that they
exist?
Additional Information: It would be useful to have a copy of a typical TCP
to show the class.
Possible Problems: None

Slide 31

1. Highway Agency (cont.)
..May include location/placement of police officers based upon:
..WZ type
..Location
..Duration
..Time of day

Key Message: Continuation of discussion of TCP.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Emphasize that a TCP is very specific, with nothing left to chance. A good TCP would specify the location of a police officer, if used.
Suggested Questions: Have you ever seen a TCP? Were you aware that they exist?
Additional Information: It would be useful to have a copy of a typical TCP to show the class.
Possible Problems: None

Slide 32

2. Contractors
..Build and maintain project
..May provide inspection services and liaison to LEO
..Ensures the traffic control is correct on a daily basis
..May be responsible for hiring and paying LEOs
..Assumes officers are trained!!
Implements the Traffic Control Plan based on the MUTCD and local standards

Key Message: Explain the "contractor" as a stakeholder in highway work zones.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: Text box appears on click. The highway agency develops the plan and they hire a contractor to implement it.
Suggested Comments: Even though contractors are working under contract, and are responsible for ensuring safe conditions, they want to maximize their profits and may be inclined to cut corners.
Suggested Questions: If a LEO sees something done incorrectly, or not according to the TCP, should they approach the contractor with his/her concerns?
Additional Information: The last bullet must be emphasized. Contractor assumes that officers know what they are doing, and perhaps because of intimidation, hesitate to talk to officers, even when thy see they are doing something incorrectly. Officers should try to establish a line of communication with the contractor and encourage the exchange of information. In some states, the contractor does not hire for nor manage the work zone enforcement program (the DOT may do it).
Possible Problems: None

Slide 33

Contractors...
..Do not have the authority to place officers contrary to established procedures and/or endanger the police officer
..Request a briefing from the contractor or DOT representative!

Key Message: Explain what contractors can ask LEOs to do.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: If officers are asked by contractors to perform an action that the officer feels is not safe, they should refuse. If LEOs feel uneasy about their safety, they should contact the contractor or the highway agency for a briefing. Express your concerns openly.
Suggested Questions: Have you even been in a position where you did not feel safe?
Additional Information: None
Possible Problems: Participants may indicate that this is not practical. Explain that their safety is critical and should not be compromised.

Slide 34

Contractors...
..Should provide a daily work zone briefing to police officers prior to the beginning of each shift or special enforcement activity.
The officer you are relieving is another good source of work zone information, but not your only one!

Key Message: Explain what officers should do when arriving at a work zone
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: It is important for the officer to receive information about the work zone. Chances are the officer has not seen the TCP. Where should he/she get the information? The most likely source is the officer they are relieving, if any. This may not be the best source. The best source is the contractor's point of contact. Contractors should brief officers on their tasks, hours of operation, what to do, what not to do, and other aspects related to the work zone. The LEO should ask questions freely.
Suggested Questions: Where should this briefing be conducted? Away from moving traffic and preferably before the project starts.
Additional Information: " . . . Each shift or activity." The enforcement operation may only be for a Phase change or lane shift.
Possible Problems: None

Slide 35

3. Contractor's Point of Contact (POC)
..Represents the Contractor in the field
..In charge of project
.."Work Zone Supervisor?
..Certification?
..DOT Inspector may be your POC - be sure of your communication channels
..Responsible for inspection and documentation
Know your primary contact in the field!

Key Message: Explain the "POC" as a stakeholder in highway work zones.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: The highway agency develops the plan and they hire a contractor to implement it. The contractor assigns a person to be their representative in the field, the "person in charge". Usually, this person is a
"Traffic Control Supervisor", or TCS. The LEO should identify who this
POC or TCS is and establish a line of communication with this person. The
TCS may be certified to perform this job. Most states require certification, or
at least some type of work zone training.
Suggested Questions:
Additional Information: The last bullet must be emphasized. The TCS should document all aspects related to the work zone. He/she is the person responsible for inspecting the work zone during installation, operation and removal.
Possible Problems: None

Slide 36

4. Traffic Control Technicians
..Report to the WZ Supervisor
..Workers
..Are good technical sources on TCP issues
..Should have some WZ training
..Understand and support role of law enforcement

Key Message: Explain the "Technician" as a stakeholder in highway work zones.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Technicians are field people, workers. They report tothe TCS. They follow the TCS instructions and help implement the TCP inthe field. They should have some type of work zone training. Some states require work zone training and certification for technicians. However, officers should not assume that technicians are trained and know what they are doing. Also, do not assume that technicians will approach officers with their concerns. The officer may intimidate them. Because of that, officers should try to be friendly with technicians in the field, to encourage two-way communication.
Suggested Questions: What are your experiences with traffic control technicians?
Additional Information: None
Possible Problems: None

Slide 37

5. Law Enforcement Officers
..Should:
..Be trained in basic work zone operations and safety
..Obtain names & numbers of contractor personnel and POC
..Attempt to make daily contact with Contractor or DOT personnel.
..Attend the project's pre-construction conference

Key Message: Explain the "LEO" as a stakeholder in highway work zones.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: None
Suggested Comments: The Slide lists things that the LEO should do. These are not requirements but recommendations. Training is one of those. All LEOs working in highway work zones should be trained, in a course similar to this one. It is also recommended that they attend the pre-construction conference, which is discussed in the next Slide.
Suggested Questions: Officers may not be aware of the pre-construction conference and may say that their attendance is not practical. They may not be notified/invited to these meetings. Encourage them to establish communication with the highway agencies to be notified of upcoming projects and meetings. One person may be a central point of contact for all
LEO details.
Additional Information: None
Possible Problems: None

Slide 38

The "Pre-construction Conference"
..A meeting where everyone involved with the project discusses:
..Roles and responsibilities
..Construction details
..Procedures/schedules are discussed
..Decisions are made
..Questions are answered
LEOs should attend and take information back to others!

Key Message: Explain the pre-construction conference.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: The pre-construction conference is organized by the highway agency. Its purpose is to inform all stakeholders in the project, to avoid surprises in the future. It results in everyone having the same information. Usually, the TCP is discussed. This is the ideal place for LEOsto ask questions and express concerns. If only one officer attends, this officer should brief other officers that may be working on the project.
Suggested Questions: How do you become aware of these meetings? Do you see a benefit in attending?
Additional Information: None
Possible Problems: Officers may not be aware of the pre-construction conference and may say that this is not practical. They may not be notified/invited to these meetings. Encourage them to establish communication with the highway agencies to be notified of upcoming projects and meetings.

Slide 39

5. Law Enforcement Officers
..Your activities will affect everyone's safety!
Anyone working in close proximity to traffic is in danger!
Watch your back!!
Your badge does not protect you from traffic impacts!

Key Message: Emphasize the safety of officers.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Bottom text box appears on click. Center text box appears on second click.
Suggested Comments: The fact that you are a police office won't help you if
a drunk driver is approaching you at 80 mph. The authority that you represent won't stop that motorist. Always position yourself in the safest possible place and NEVER assume that a motorist will stop just because you are a police officer. The badge you wear won't protect you!
Suggested Questions: Who is in danger in a work zone?
Additional Information: None
Possible Problems: None

Slide 40

Main Types of Police Services in WZ
a) Presence
b) Enforcement
c) Traffic Control
d) Emergency assistance

Key Message: Introduce the four services of LEOs working in highway
work zones
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: List the four types
Suggested Questions: None
Additional Information: Do not elaborate on these types. The following Slides expand on each of these services.
Possible Problems: None

Slide 41

Services:
a) Presence
..Deterrent to speeding and aggressive driving
..Gains the attention of drivers
Most common LEO activity in WZ!

Key Message: Introduce the first service: Presence
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: Presence is the most common use of LEOs in workzones. It involves a positioning an officer within the work zone, to be
VISIBLE and deter speeding. Officers must be visible for this service to be effective. It is important to note that officers ARE NOT enforcing speed limits at this point, just deterring speeding through their PRESENCE alone. LEOs may be paid by the contractor when working "off-duty". The fact that an officer is "off-duty" does not mean he/she is immune from danger. (See
Possible Problems below.) The officer must be alert at all times. Avoid doing paper work and any other activities that may distract you. You are still in danger.
Suggested Questions: What experiences have you had?
Additional Information: None
Possible Problems: Trainees may try to engage in a discussion of the differences between "on-duty" and "off-duty". Avoid this discussion.
Indicate that the definitions vary. What is important is the task that the officer is performing.

Slide 42

Presence Issues
..Jurisdictional boundaries may cause issues
..Work zone impact area may cross boundaries
..Longer queuing and higher traffic impacts
..Multi-agency traffic teams are an option
..Use of State Police is another option for presence officers to reduce jurisdictional issues
Have a process or policy!

Key Message: Discuss issues related to the presence activity.
Est. Presentation Time: Depends on discussion
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: Discuss these issues as needed. Give examples as needed. A good example is the Washington DC area where the Washington
Beltway crosses Virginia, Maryland, and Washington, DC. Who is in charge?
What if a queue formed in one state reaches another one?
Suggested Questions: Why longer queuing? Traffic slows down!
Additional Information: None
Possible Problems: None

Slide 43
Services:
b) Enforcement
..Active enforcement of traffic laws in the WZ
..May not be as common as presence
..Combine with presence
WZ should be enforced as strictly as school zones!
Presence officers shouldn't do enforcement! Use local officers.

Key Message: Introduce the second service: Enforcement
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Top text box appears on click. Second box appears on second click.
Suggested Comments: Officers enforce speed limits by writing speeding tickets. This is not the same as presence. Under this service, officers are actively enforcing the speed limit. These officers are "on-duty" and may not be paid by the contractor. (See Possible Problems below.) Encourage officers to enforce speed limits in work zones as they do in school areas, topersuade drivers to SLOW DOWN in work zones. State police officers may have a larger range on a large project for presence and may have fewerjurisdictional issues - local officers may be better for spot enforcement.
Suggested Questions: What experiences have you had?
Additional Information: None
Possible Problems: Trainees may try to engage in a discussion of the differences between "on-duty" and "off-duty". Avoid this discussion.
Indicate that the definitions vary. What is important is the task that the officer is performing.

Slide 44

Services:
c) Traffic Control
..Operations that rrequire traffic controlsuch as intersections
..May be used in detour/diversion situations
..Or to direct traffic & keep it moving
This may be in line with normal duty for a police officer

Key Message: Introduce the third service: Traffic control
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: Officers control traffic according to the requirements of the work zone. This is an "on duty" task. (See Possible Problems below.) A typical application is when traffic must be controlled within an intersection due to the construction (or a crash). In several states, flaggerscannot legally perform this task; only police officers can. The State of
Massachusetts does not allow flaggers at all. Police handle all flagging situations.
Suggested Questions: What experiences have you had?
Additional Information: None
Possible Problems: Trainees may try to engage in a discussion of the differences between "on-duty" and "off-duty". Avoid this discussion.
Indicate that the definitions vary. What is important is the task that the officer is performing.

Slide 45

Services:
d) Emergency Assistance
..Not within the scope of this class
...Emergency traffic control is a type of temporary traffic control
..Discussed in section 6i of MUTCD

Key Message: Introduce the fourth service: Emergency Assistance
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: This service is outside of the scope of this class, which is for the use of LEOs in planned work zones. Indicate that emergency traffic control is considered a subset of temporary traffic control and the same procedures apply. The 2003 MUTCD does contain a section (6i) dedicated to incident management practices that can be reviewed.
Suggested Questions: None
Additional Information: Section 6i allows the use of fluorescent pink signs for emergency traffic control.
Possible Problems: Avoid engaging in a discussion on this subject, just indicate that this is another type of service. Not within the scope of this class.

Slide 46

What to do When Working in a Work Zone
1. Stay in communication
2. Be visible
3. Be alert
4. Drive-through
5. Investigate crashes?
6. Arrive early/leave late
7. Monitor TCP compliance?
Let's discuss in more detail!

Key Message: List some activities LEOs should do when working in a work zone.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: Included in the list are things that officers should do when working in a work zone. Avoid discussing these in detail since the following Slides do that. The last bullet does have a question mark since you want to generate discussion on that subject.
Suggested Questions: Others?
Additional Information: These are recommendations, not requirements.
Possible Problems: Do not describe these at this point.

Slide 47

1. Stay in Communication
..Report to the POC at beginning of shift
..Contact Project Engineer for clarification and directions
..Remain in radio contact with the local dispatch

Key Message: Discuss COMMUNICATION.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Discuss why staying in communication is important.
Identify the POC ahead of time and ask questions about the work zone.
Make sure you understand the work zone and what your role is. Ask about your position and express concerns about your safety if any. While in your car, stay in communication with the local dispatch. It is also a good idea to be in communication with the POC, in case you have to move, for example.
Suggested Questions: How can you communicate with the POC?
Additional Information: None
Possible Problems: Officers in the class may be new with this idea and may reject it. Emphasize its benefits.

Slide 48

What to discuss with the Point of Contact (POC)
..Project objective and schedule
..Your location
..Contact information
..Identify enforcement areas?
..Express concerns about your safety, if any
..Be friendly!

Key Message: Discuss things you need to communicate (discuss) with the POC.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory. Discuss "what if" scenarios.
Friendliness will open communication channels. Technicians are often intimidated by police.
Suggested Questions: Any other?
Additional Information: None
Possible Problems: None

Slide 49

2. Be Visible
..Patrol car emergency lights on
..No headlights
..If outside the patrol vehicle and within the work zone, MUST wear issued retro reflective safety vest
Your visibility is critical!

Key Message: Discuss the importance of visibility, both the patrol vehicle and the officer himself/herself.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: When working in the presence mode, your patrol vehicle has to be visible to be effective. Use your emergency lights, not your headlights, particularly if facing traffic. If you need to be outside your vehicle for any reason, make sure you wear a retro reflective vest, day or night.
Suggested Questions: Why should you wear a vest during the day? What color are most police uniforms?
Additional Information: American National Standards Institute (ANSI)
Class 2 vests are recommended.
Possible Problems: The concept of daytime vests may be controversial since some officers may be reluctant to do this. Reinforce the benefits: enhanced visibility, even during the day.

Slide 50

Where is the safest place to be for PRESENCE?
..Identify the safest and most efficient location, that is in compliance with procedures
..Will discuss in next module

Key Message: Continue discussion of visibility.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: When working in the presence mode, your patrol vehicle has to be visible to be effective. Where can you be effective AND safe? This will be discussed in the next module but it is here to generate interest and make them think.
Suggested Questions: On the closed lane? On the shoulder? Where?
Additional Information: None
Possible Problems: Avoid giving the answer at this point. Keep them thinking and guessing.

Slide 51

3. Be alert
..Stay alert at all times!

Key Message: Discuss alertness
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Even if you are visible, you must be alert, paying constant attention to traffic. Keep your eyes open. Ask yourself: What would
I do if a car is heading my way? Determine an escape route. Avoid getting blocked by guardrails, etc.
Suggested Questions: Why do you need to be alert? What things can distract you? (Falling asleep, doing paper work, watching movies, etc.)
Additional Information: None
Possible Problems: None

Slide 52

4. Drive-Through
. Both directions
. To become familiar with the work zone and its activities
. To determine safe places to investigate crashes and for enforcement
. To identify hazardous conditions

Key Message: Discuss the drive-through
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Emphasize why the drive-through is important. Self-explanatory. The more information about the work zone that you have, the better.
Suggested Questions: Why is this important? When should you do this?
Additional Information: None
Possible Problems: None

Slide 53

5. Investigate Crashes
..Investigate minor property damages crashes that occur within the WZ if the time required to complete the investigation is minimal
Crashes involving injury shall be investigated by the appropriate personnel, not the WZ "presence" officer. Determine local property damage (PDO) policies ahead of time!

Key Message: Discuss the possibility of investigating minor crashes.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: Top text box appears on click. Second box appears on second click.
Suggested Comments: Treat this Slide as a question to generate discussion.
Remember that "presence" officers are typically "off-duty". Because of that, crashes should be investigated by "on-duty" officers. Also, investigating crashes would required "presence" officers to abandon their position, which may result in increased speeds and secondary crashes. When working as "presence", avoid investigating crashes.
Suggested Questions: How do you feel about this? What would you do if there's a crash in the work zone?
Additional Information: None
Possible Problems: None

Slide 54

About Investigating Crashes..
. Limit investigation of minor property-damage crashes to assurance of non-injury. Crashes involving injury should be investigated by the appropriate personnel, not the WZ "presence" officer. Enforcement agency policy will guide initial involvement. Determine local property damage only (PDO) policies ahead of time!

Key Message: Discuss crash investigation.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: Top text box appears on click. Second box
appears on second click.
Suggested Comments: Expand on the point from previous Slide: "Presence" officers are typically "off-duty". Because of that, crashes should be investigated by "on-duty" officers. Also, investigating crashes would require "presence" officers to abandon their position, which may result in increased speeds and secondary crashes. When working as "presence", avoid investigating crashes.
Suggested Questions: What experiences do you have? What benefits do you see to having a pre-established procedure or policy?
Additional Information: None
Possible Problems: Some officers may disagree with this. Be prepared to defend your point.

Slide 55

6. Arrive early/leave late
..For best worker protection, be present when the traffic control devices are being installed or removed

Key Message: Recommend arriving early and leaving late
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: "15-Minute Rule!" appears on click.
Suggested Comments: Recommend arriving early to gather as much information as possible, driving through, and identifying your POC.
Suggested Questions: How early?
Additional Information: Recommend 15 minutes early, which is called the
15-minute rule. This is a courtesy, a recommendation.
Possible Problems: Attendants may not be aware of this concept and may
reject doing this. Again, emphasize the benefits and the fact that this is a recommendation, a courtesy. It also enhances the officer's safety.

Slide 56

As a courtesy: The 15 Minute Rule .......
..Arrive 15 minutes before traffic control devices are being placed, moved or taken down
..Stay 15 minutes after these changes have taken place, to ensure the new traffic control change is working properly
Discuss with POC

Key Message: Explain the 15-minute rule
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: "15-Minute Rule!" appears on click. Text box
appears on second click.
Suggested Comments: Self-explanatory. This is a courtesy, not a
requirement.
Suggested Questions: Have you ever done this? Why?
Additional Information: None.
Possible Problems: Attendants may not be aware of this concept and may
reject doing this. Again, emphasize the benefits and the fact that this is a
recommendation, a courtesy. It also enhances the officer's safety.

Slide 57

..Inspect TCP compliance?????????
..Check TCP against field inspection
..Detect safety violations
..Notify supervisor of problems
..Inspect TCP Compliance?
Officers are not responsible for TCP inspection, but can be extremely valuable in identifying potential problems.
NJ State Police has a program....

Key Message: Discuss the possibility of enforcing TCP compliance
Est. Presentation Time: 1-2 minutes depending on discussion
Explanation of Cues/Builds: Top box appears on click. Bottom text box appears on second click.
Suggested Comments: This will be controversial and possibly rejected since it is a new concept. Ask, how do you feel about inspecting for compliance with the TCP? Can we enforce TCPs? The State of NJ has a program to do exactly this. This is discussed in the next Slide.
Suggested Questions: If you see something that is not right in the work zone, what would you do?
Additional Information: Even if the officer is not authorized to enforce TCPs, as a citizen, if an unsafe condition is detected, isn't our responsibility to notify someone? Play devil's advocate.
Possible Problems: Attendees may not be aware of this concept and may reject doing this.

Slide 58

NJ Safety Intervention Results: July 1, 1995 -November 30, 2000
5248 Total Interventions
11,544 Employees Removed From Risk
3387 OSHA Violations Corrected
4008 DOT Violations Corrected
247 Different Contractors Impacted

Key Message: BRIEFLY discuss the NJ Program for work zone interventions by police.
Est. Presentation Time: 1-2 minutes depending on discussion
Explanation of Cues/Builds: None
Suggested Comments: The New Jersey State Police has a program to intervene (enforce) in work zones that are not safe (not according to the standards, safe practices and/or TCP). The Slide lists the "intervention" statistics for the period.
Suggested Questions: Do you think a program like this would work in your state? What are the benefits? Pros? Cons?
Additional Information: OSHA = Occupational Safety and Health Administration, DOT = Department of Transportation.
Possible Problems: Attendants may not be aware of this concept and may reject doing this.

Slide 59

DISCUSSION
..How do you feel about requiring training for officers before they work in or around traffic work zones?

Key Message: Discussion Slide
Est. Presentation Time: Depends on discussion. Use your judgment.
Explanation of Cues/Builds: None
Suggested Comments: Generate discussion. Emphasize the importance of
training.
Suggested Questions: What about certification? Who should provide this
training/certification? Discuss.
Additional Information: None
Possible Problems: None

Slide 60

Module Recap
..What are the traditional roles of LEOs in work zones?
..Who else is involved with work zones?
..What specific activities are typical of LEOs in work zones?
..What is the "15-Minute Rule"?
..Do you know your POC?
..Do policies related to emergency response exist?

Key Message: Recap Slide
Est. Presentation Time: 2-3 minutes
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory. Try to gauge understanding by
asking these questions and others.
Suggested Questions: Shown.
Additional Information: None
Possible Problems: None

Slide 61

Understanding Work Zones
Session Title: Module 2. Understanding Work Zones
Performance-Based Learning Outcomes: Understand the fundamentals (basic concepts) of work zone projects.
Instructional Method: Lecture
Session Time: 46 Slides. Approximately 60 minutes depending class participation.
Evaluation Plan: Evaluate learning outcomes at the end of each module using the questions contained in the last Slide of that module and through the exercises.

Slide 62

Module Objectives
..Discuss sources of WZ standards & guidelines
..Define the component parts of a TTC zone
..WZ terminology
..Discuss patrol vehicle positioning

Key Message: List module objectives.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: None
Additional Information: TTC means Temporary Traffic Control - TTC zone is a work zone.
Possible Problems: None

Slide 63
Where Can Federal WZ Standards be Found?
..Manual on Uniform Traffic Control Devices (MUTCD)

Key Message: Indicate where Federal standards and guidelines can be found.
Est. Presentation Time: Less than one minute
Explanation of Cues/Builds: "Uniformity" appears on click.
Suggested Comments: Federal standards and guidelines can be found in the
MUTCD, published by FHWA (Federal Highway Administration), part of
the US Department of Transportation (DOT). The purpose of this document
is to provide for the uniformity of traffic control devices nationwide. The
current edition is the 2003 edition. This documents applies to all states and
territories, according to the Code of Federal Regulations (CFR), Title 23.
Suggested Questions: Why do we need uniformity?
Additional Information: Standards are different from guidelines. Standards
are normally requirements, guidelines are recommendations.
Possible Problems: None

Slide 64

Manual on Uniform Traffic Control Devices
..MINIMUM standards
..States and local agencies can have more restrictive standards
..Applies to ALL streets and highways open to the public travel

Key Message: Describe the extent/application of MUTCD standards.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: The MUTCD establishes "minimum" standards and
guidelines, applicable everywhere in the U.S. States and territories may have
their own standards as long as they are more strict (restrictive) than the
MUTCD.
Suggested Questions: What is a "minimum" standard? May give the
example of the height of cones. The MUTCD requires cones used on
freeways to be 28" high, as a minimum, but several states require 36" cones.
Additional Information: None
Possible Problems: None

Slide 65

The MUTCD
..Does not address use of law enforcement officers in WZ
..Does not show location of police vehicles

Key Message: Indicate limitations of MUTCD when it comes to the use of
LEOs in work zones.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: These limitations mean that specific information
about the use of LEOs is lacking. Their use would be subjective, within the
guidelines of the MUTCD. However, the MUTCD does not address LEOs
specifically.
Suggested Questions: What do we do if specific standards do not exist?
What problems would that create? Answer: Lack or uniformity and
improper practices.
Additional Information: States may have their own, more specific,
guidelines.
Possible Problems: Attendants may be critical of the MUTCD. Indicate that
the MUTCD gives a framework for protecting "workers" (and users). LEOs
may be considered workers and the same principles would apply. But in the
case of LEOs the information is not specific.

Slide 66

Parts of a WZ
Advance Warning Area
Transition Area
Termination Area Buffer Space
Activity Area Work Space
Traffic Space

Key Message: Describe the Component Parts of a Typical Work Zone.
Est. Presentation Time: 5 minutes
Explanation of Cues/Builds: Each of the component parts appears on click,
starting from the bottom.
Suggested Comments: Even though the following Slides discuss each part in
detail, spend some time on this Slide. Indicate this is an example of a right lane
closure on a 4-lane divided highway. Go over each of the parts, describing its
purpose. For example, the ADVANCE WARNING AREA provides warning to
motorists about the situation ahead, and the required action. In this case, it
would be: ROAD WORK AHEAD, RIGHT LANE CLOSED, MERGE RIGHT.
Suggested Questions: Is this the way you see work zones in the field? Does this
look familiar?
Additional Information: This is a 4-lane divided highway, but only the two
northbound lanes are shown. Indicate that this IS NOT a two-lane road.
"Divided" refers to presence of a median. "Undivided" highways only have a
painted line to separate opposing flows.
Possible Problems: Avoid giving too much detailed information at this point.
This is to illustrate terminology only. Specific information is given in the
following Slides.

Slide 67

1. Advance Warning Area
..Uses advance warning signs to warn drivers
..Where drivers make their decisions!
No warning = Surprise!! = Erratic Maneuver = Crash

Key Message: Describe the Advance Warning Area (AWA).
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: The AWA is critical to a work zone. Without it,
drivers would be surprised, which could lead to erratic maneuvers and
crashes. Proper warning allows time for drivers to understand the situation
ahead and the required actions. EVERY work zone should have an AWA.
Suggested Questions: What would happen if a lane closure is missing the
AWA? How do we warn motorists? Warning signs and supplemental
devices such as message boards.
Additional Information: None
Possible Problems: None

Slide 68

Advance Warning Signs
..Usually, 3-step process:
..1st sign: Gets their attention
..2nd sign: Tells the problem
..3rd sign: Tells them what to do
..Diamond shape
..Orange in WZ
..48" x 48"

Key Message: Indicate the subcomponents of the AWA.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Usually (not necessarily, particularly in low-speed
areas) the 3-step process is used in the AWA. Some states use additional
signs. Warning signs are diamond-shape and orange, to indicate a
temporary conditions. Signs used in "high-speed areas" shall be at least 48"
x 48". Smaller signs may be used in lower speed areas. Indicate that this is a
State preference and they should consult their local standards. The
instructor may want to become familiar with the local standards.
Suggested Questions: None
Additional Information: None
Possible Problems: Indicate that this is a State preference and they should
consult their local standards. The instructor may want to become familiar
with the local standards.

Slide 69

MUTCD Suggested Advance Warning Sign Spacing
* Speed determined by local agency

Urban (low speed*) :: Road Type A=100' Road Type B=100' Road Type C=100'
Urban (high speed*) :: Road Type A=350' Road Type B=350' Road Type C=350'
Rural :: Road Type A=500' Road Type B=500' Road Type C=500'
Freeways and Expressways :: Road Type A=1000' Road Type B=1500' Road Type C=2640'

Key Message: Discuss Sign Spacing in the AWA.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: None
Suggested Comments: This table shows the sign spacing suggested in the
MUTCD. The following Slide shows what A, B and C are, but they refer to
the spacing between signs, when the 3-step process is used. Advance to the
next Slide to illustrate this point and then return to this one.
Suggested Questions: What would happen if the signs are much closer than this? Motorists would not have the necessary time to make their decisions
and take the required action. What is "low speed"?
Additional Information: The breakpoint between low speed and high speed is called the "threshold speed". It varies by jurisdiction but it is typically between 35 and 40 mph.
Possible Problems: Indicate that this is a State preference and they should consult their local standards. The instructor may want to become familiar
with the local standards. Also notice this is not a requirement because
sometimes it is not possible. If this spacing is not possible, suggest to
increase it, not to decrease it. Also, be prepared to define "urban" and
"rural". Urban areas are not restricted due to heavier traffic, pedestrians andother obstructions. Define freeways and expressways as the same: Limited
access, where access is only through ramps, not intersections.

Slide 70

Parts of a WZ
A
B
C

Key Message: Define A, B and C.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: See previous Slide for guidance on this Slide.
Suggested Questions: None
Additional Information: Indicate that A is the distance to the sign closest tothe work space.
Possible Problems: None

Slide 71

Sign spacing is critical!
To give TIME to analyze and decide on maneuver

Key Message: Describe the importance of proper sign spacing.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Meant to be funny. Illustrates how time translates
into distance. The closer the signs, the less time motorists will have to make
their decisions.
Suggested Questions: How much time is enough time at 65 mph?
Additional Information: None
Possible Problems: Instructor may hide Slide if desired.

Slide 72

Portable Changeable Message Signs (PCMS)
..Sometimes used before the advance warning area
..Supplemental devices
..Optional devices

Key Message: Describe use of PCMS.
Est. Presentation Time: Less than 1 minute.
Explanation of Cues/Builds: None
Suggested Comments: PCMSs are sometimes (optionally) used as
supplemental devices prior to the AWA. Supplemental means used "in
addition" to static signs, never as a replacement (in lieu of). They may also
be used for incident management.
Suggested Questions: Why are PCMS supplemental? Because they may
malfunction, cannot be relied upon.
Additional Information: "Message board" is a lay term for a PCMS. PCMSs
come in various sizes. Scrolling text is not permitted. Abbreviations and
messages must be pre-approved and included in the TCP. They shall be
dimmed (50%) for nighttime use.
Possible Problems: Avoid an over-technical discussion.

Slide 73

..Typically uses channelizing devices to form a taper
2. Transition Channelizing devices
A taper is a gradual transition

Key Message: Define tapers.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: Define the taper as a gradual transition, from one
condition to another. There are various types of tapers. This one illustrates a
"merging" taper, which is used on lane closures. These tapers are long so
traffic can maintain speed. Short tapers encourage drivers to slow down,
leading to congestion. Later in the class we discuss a minimum length for
these tapers. Channelizing devices (cones, barricades, drums [next Slide]) are
used to create tapers.
Suggested Questions: Should these tapers be short or long? Why?
Additional Information: None
Possible Problems: None

Slide 74

Channelizing Devices
..Cones
..Two white bands for night use!
..Short duration only
..Drums
..Others

Key Message: Define channelizing devices
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Define channelizing devices as objects used to
"channelize" or "delineate" (create lines). The Slide illustrates cones and
drums only, perhaps the most common. Barricades and tubular markers are
also channelizing devices. The use of cones is very limited; usually short
duration projects because they need to me maintained. If cones are used at
night, they shall have the two retroreflective bands shown. Drums are
common in long term projects (unattended).
Suggested Questions: None
Additional Information: The MUTCD requires cones used on freeways to
be at least 28" high. Several states require 36" cones. Drums are also 36"
high.
Possible Problems: None

Slide 75

Minimum length of MERGING taper (L) in feet necessary to close a 12-ft lane
Speed = 25 Length = 125
Speed = 30 Length = 180
Speed = 35 Length = 245
Speed = 40 Length = 320
Speed = 45 Length = 540
Speed = 50 Length = 600
Speed = 55 Length = 660
Speed = 60 Length = 720
Speed = 65 Length = 780
Speed = 70 Length = 840
Speed = 75 Length = 900

Key Message: Define the MINIMUM length of MERGING tapers.
Est. Presentation Time: 2minutes
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: Table shows the minimum length of a merging taper,
necessary to close a 12-foot lane. Most freeway lanes are 12 feet wide, so this
table would apply to most lane closures on freeways. These figures are
minimums. The length could be more, but not less. To a certain point, the
longer the taper, the smoother traffic will flow.
Suggested Questions: How long is a football field? 300 feet. For a 55 mph
zone, a merging taper would be over 2 football fields in length.
Additional Information: These figures are a function of the speed of traffic
and the width of the lane. For narrower lanes, shorter tapers may be
acceptable according to formulas presented in the MUTCD. The speed used
IS NOT the posted speed but the "prevailing" speed in the area.
Possible Problems: Avoid a technical discussion. This table only illustrates
that tapers are carefully planned and that there are requirements for their
lengths. Avoid discussing formulas.

Slide 76

One-Lane Two-Way Taper 50-100' MAX
..On two-lane roads
..Flaggers required
.."Flagging taper"

Key Message: Illustrate a flagging taper.
Est. Presentation Time: 1 minutes
Explanation of Cues/Builds: None
Suggested Comments: Slide illustrates how "flagging tapers" are an
exception to the previous Slide. These tapers are used on two-lane roads
where one lane is closed. This requires flaggers (or portable signals).
Because the flaggers need to slow down and sometimes stop traffic, a short
taper is used, as shown.
Suggested Questions: Why do we need a short taper in this situation? What
is a "two-lane road"?
Additional Information: Arrow panels (displaying an arrow) are never
used in two-lane roads, since they would direct traffic into an oncoming
lane.
Possible Problems: Do not elaborate too much. Slide is only here because it
is an exception to the explanation from the previous Slide (a special case) .

Slide 77

Speeds are Critical in Work Zones!
..The faster the speed:
..The less time motorists will have to make their maneuvers
..The more severe the crash
This is called "Perception-Reaction Time"

Key Message: Relate time to distance.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: At high speeds, motorists have less time to make
their decisions and maneuvers.
Suggested Questions: How much time do we need, as humans, in order to
perceive, analyze, and react to a situation? That time is caller PRT, or
perception-reaction time. The answer is given on the next Slide.
Additional Information: None
Possible Problems: None

Slide 78

Perception-Reaction Time (PRT)
..The amount of TIME drivers need to perceive, analyze, react and complete their maneuvers
PRT= 2.5 sec. under "normal" conditions
PRT= 5+ sec. for work zones!!!

Key Message: Define PRT.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Left text box appears on click. Right text box
appears on second click.
Suggested Comments: "Normal" refers to every day, familiar situations. In
a work zone, the PRT is typically twice as long, or even longer; 5-7 seconds.
This is the time we need as humans. PRT is a "human factor".
Suggested Questions: Why would the PRT be longer in a work zone?
Because drivers need more time to analyze a situation that is not familiar to
them. [maybe also because there is more visual information to analyze-
advance warning signs, cones, maybe a PCMS, maybe a flagger, vehicles
entering roadway, etc.]
Additional Information: None
Possible Problems: None

Slide 79

Converting mph to fps
..Multiply the speed in miles per hours by 1.47 to obtain the number of feet
a vehicle travels in one second
Example:
60 mph = (60)(1.47) = 88 fps
At 60 mph you travel 88 feet
in ONE second!

Key Message: Understand how much distance we cover in one second
when traveling at certain speed.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: Top text box appears on click. Bottom text box
appears on second click.
Suggested Comments: Ask participant simply to remember the number
1.47. When you multiply speed in miles per hour by 1.47, you convert speed
to feet per second, or the number of feet you would travel at that speed in
one second. This is meant to be an eye opener, to help them realize the
distance you would cover in one second at a certain speed.
Suggested Questions: If you cover 88 feet in one second, how many feet
would you cover during the PRT? [in a work zone, at least 440 feet: 5
seconds x 88]
Additional Information: None
Possible Problems: None

Slide 80

ESTIMATING TIP:
Converting mph to fps
..Approximate by using 1.5
..The number plus its half
Example:
60 mph = 60 + 30 = 90 fps

Key Message: Provide tip to approximate the point made on previous Slide.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: If you do not have a calculator or if you are not a
math wiz, use this technique to approximate, to get a mental picture of the
distances covered in one second at certain speeds.
Suggested Questions: NASCAR fans: How many feet do you cover in one
second at 200 mph? Answer: Approximately 300 ft, or 200 + 100.
Additional Information: None
Possible Problems: None

Slide 81

Speed (mph) :: Feet Traveled in One Second
25 :: 37
35 :: 51
45 :: 66
55 :: 81
60 :: 88
65 :: 96
75 :: 110
80 :: 118
Feet Traveled in One Second

Key Message: Table to illustrate/expand on previous Slide.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: The example from the previous Slide is in this table
(60 mph).
Suggested Questions: If you cover this many feet in one second, how many
feet would you cover during the PRT? Answer: Multiply these numbers by
2.5 for normal conditions and by 5 for work zones. This is illustrated in two Slides.
Additional Information: None
Possible Problems: None

Slide 82

Distance (ft) Traveled During the PRT
*Football Field = 300 ft.!!

Speed = 25mph :: Distance Traveled in 2.5 sec = 92 :: Distance Traveled in 5.0 sec = 183
Speed = 35mph :: Distance Traveled in 2.5 sec = 129 :: Distance Traveled in 5.0 sec = 257
Speed = 45mph :: Distance Traveled in 2.5 sec = 165 :: Distance Traveled in 5.0 sec = 331
Speed = 55mph :: Distance Traveled in 2.5 sec = 202 :: Distance Traveled in 5.0 sec = 404
Speed = 60mph :: Distance Traveled in 2.5 sec = 220 :: Distance Traveled in 5.0 sec = 440
Speed = 65mph :: Distance Traveled in 2.5 sec = 239 :: Distance Traveled in 5.0 sec = 478
Speed = 75mph :: Distance Traveled in 2.5 sec = 276 :: Distance Traveled in 5.0 sec = 551
Speed = 80mph :: Distance Traveled in 2.5 sec = 294 :: Distance Traveled in 5.0 sec = 588

Key Message: Relate speed to the number of feet covered during the PRT.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: "Football Field" appears on click, to relate the
distances on the table to a visual picture.
Suggested Comments: Table illustrates the distances, in feet, covered at certain
speed during the PRT. These figures come from multiplying the previous table by
2.5 and 5.0. Emphasize that at 65 mph, you cover 478 feet in 5 seconds, the PRT for a
work zone.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 83

Arrow Panels
..Supplemental device
..Used in addition to signs
Arrows are used ONLY when a lane is closed and merging is required

Key Message: Introduce arrow panels.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Arrow flashes continuously.
Suggested Comments: Arrow panels are supplemental devices, used IN
ADDITION to static signs. Arrows are displayed only when lanes are closed.
Suggested Questions: Why are arrow panels supplemental? Because they
may malfunction.
Additional Information: Arrow panels and arrow boards may be used
interchangeably.
Possible Problems: None

Slide 84

The "CAUTION"Mode
..Displayed for shoulder operations
..No arrows if all lanes are open

Key Message: Discuss the "CAUTION" mode.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: The "caution" mode is used for shoulder operations,
or when all lanes are open but we wish to "caution" or warn motorists about
a condition ahead. Shoulder work is the most common example. The sign
displays four corners flashing or a flashing bar (not shown).
Suggested Questions: Have you ever seen this mode?
Additional Information: It is quite common (unfortunately) to see shoulder
work with an arrow being displayed. The caution mode should be used
instead. Some states prefer the four corners over the flashing bar since the
bar may be confused with a malfunctioning arrow.
Possible Problems: None

Slide 85

Use of the Mode for Work "CAUTION" Shoulder
Key Message: Display example of point made in previous Slide.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Notice the use of the CAUTION mode for shoulder
operations, in this case on a short-term project on a two-lane road, where the
display is mounted on a truck-mounted attenuator.
Suggested Questions: None
Additional Information: Fast Slide to illustrate the point made in previous Slide.
Possible Problems: None

Slide 86

Preferred Arrow Panel Location
..For a stationary lane, panel should be located on the shoulder at the beginning of the taper

Key Message: Describe the preferred location of the arrow panel for lane
closures.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: This is the preferred location, on the shoulder at the
beginning of the taper. If there is no shoulder, then it should be located
inside the taper as close to the merge point as possible.
Suggested Questions: What if there is no shoulder?
Additional Information:
Possible Problems: None

Slide 87

3. Activity Area
..3 Sub-areas
..Buffer space
..Work space
..Traffic space

Key Message: List the three sub-areas of the activity area.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: None
Additional Information: None
Possible Problems: Just list them. The following Slides will discuss each of them in detail.

Slide 88
Buffer
Space
Work
Space
Traffic
Space
Not to
scale
Area
3. Activity
Key Message: Illustrate where the activity area fits within the typical
work zone.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 89

..Recovery area for errant vehicles
..Protects workers
..ALWAYS empty
..No vehicles or equipment allowed
..Highly recommended Buffer Space
DO NOT PARK IN BUFFER SPACE!

Key Message: Discuss the buffer space.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: "A FORGIVING DESIGN" appears on first click. Text box appears on second click.
Suggested Comments: The buffer space is highly recommended. This feature separates the taper from the work area. It allows errant drivers who may drive through the taper [and what do you mean "through the taper"-actually through the cones or barrels? Or just enter the taper and get too far into it without realizing they need to move over?] a distance
to recover BEFORE reaching the work zone and injuring workers. Buffer spaces MUST be empty or they defeat their purpose. EMPTY means clear, nothing there, not a patrol vehicle, nothing.
Suggested Questions: What would happen if there is no buffer and a vehicle runs through the taper? What do you think the length of the taper will depend on? Speed! Not the posted speed, the prevailing speed!
Additional Information: Providing a buffer is considered a "forgiving design" where motorists do not pay with their lives for making a mistake, they are "forgiven". A new concept is a "caring design". If a distracted motorist runs through the taper, he/she has three options: 1) stop, 2) bail into the clear zone, or 3) bail into the traffic space. All three would minimize the severity of the crash, if it does occur at all.
Buffers are not required because sometimes they do not fit (a flexible standard). But if they fit, they should be provided according to the table on Slide 31.
Possible Problems: None

Slide 90

Do not park in buffer space!
..Your vehicle is not equipped with an impact attenuator!
..Not a "forgiving design"

Key Message: Discuss where to position a patrol vehicle on lane closures.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: None
Suggested Comments: A buffer space is always empty. A patrol vehicle in
the buffer space is not a forgiving design. Motorists who run through the
taper will impact the patrol vehicle, injuring themselves and the officer.
Unlike a TMA, patrol vehicles are not designed to be impacted.
Suggested Questions: Where should the patrol vehicle be located? Why?
Additional Information: The patrol vehicle should be on the shoulder,
within the AWA. This is discussed in detail later in this class. This is a
simple concept but affects the LEOs directly. Spend some time discussing it.
Possible Problems: This may be controversial since it may go against
current practices. Some students may reject this concept. Be ready to defend
it.

Slide 91

Stopping Sight Distance as a Function of Speed
*Use for longitudinal buffer spaces

Speed (mph) = 20 :: Buffer (ft.) = 115
Speed (mph) = 25 :: Buffer (ft.) = 155
Speed (mph) = 30 :: Buffer (ft.) = 200
Speed (mph) = 35 :: Buffer (ft.) = 250
Speed (mph) = 40 :: Buffer (ft.) = 305
Speed (mph) = 50 :: Buffer (ft.) = 425
Speed (mph) = 55 :: Buffer (ft.) = 495
Speed (mph) = 60 :: Buffer (ft.) = 570
Speed (mph) = 65 :: Buffer (ft.) = 645
Speed (mph) = 70 :: Buffer (ft.) = 730

Key Message: Discuss the length of buffer spaces.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: This table is from the 2003 MUTCD. The distances are the
distances required by a vehicle to stop at certain speed.
Suggested Questions: How long is a football field again? 300 feet. At 65 mph, a
buffer space is longer than TWO football fields.
Additional Information: These are minimum distances. If warranted, longer
distances may be used. Source: 2003 MUTCD, Table 6C-2. Stopping Sight Distance
as a Function of Speed. These distances were increased substantially from previous editions.
Possible Problems: None

Slide 92

Determining distances in the field
..Use odometer for longer distances
..1/10 mile = 525'
..Use skip pattern for short ones
..10 skips = 400'
30'
10'
40'

Key Message: How to determine distances in the field.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Text box appears on first click. Skids appear on
second click.
Suggested Comments: When determining distances in the field, you may
use your odometer for long distances and/or the "skip pattern" for short
ones. A 10-30 skip means that each line is 10 feet long and the gap between
the lines is 30 feet. So from one line to the next, there are 40 feet. Not all
skips are 10-30, so make sure you know what the pattern is.
Suggested Questions: None
Additional Information: This is a field approximation.
Possible Problems: None

Slide 93

Traffic Space
..The space open for public to pass safely

Key Message: Discuss the traffic space.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory. The traffic space is open to the public.
Suggested Questions: What is the minimum width of a traffic lane? It
depends on the type of facility and state preferences, but in general terms,
the minimum width of a freeway lane is 11 feet.
Additional Information: None
Possible Problems: None

Slide 94

4. Termination Area
..May (optionally) include
..Termination taper
..100' min.
..END ROAD WORK sign

Key Message: Discuss the termination area.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: The last component part of the termination area,
which may optionally include a "termination taper" and an END ROAD
WORK sign. The termination taper is a minimum of 100' long (per lane
reopened), and the END ROAD WORK sign is typically 500' past the last
device.
Suggested Questions: None
Additional Information: Termination tapers are usually built with 6 devices
at 10' apart.
Possible Problems: None

Slide 95

Positioning your patrol car
where
why
Based on what you've learned so far,
would be the safest place to position a patrol
vehicle for "presence"

Key Message: Discuss patrol vehicle positioning.
Est. Presentation Time: Based on discussion
Explanation of Cues/Builds: Empty text box and question mark appear on
first click. Text appears on second click.
Suggested Comments: Let's open the floor for discussion. Based on what
you have learned so far, where would you position your patrol vehicle if
working on a lane closure?
Suggested Questions: Should it be in the buffer space? In the taper? In the
termination area? Where can you be safe and at the same time effective?
Additional Information: None
Possible Problems: Attendees may be reluctant to initiate discussion. Be
prepared to ask questions and play devil's advocate.

Slide 96

..BEFORE the transition
..NOT IN BUFFER
..On the SHOULDER or MEDIAN
..Between the 2nd and 3rd sign
..Where we need the motorists
to pay most attention to what
they need to do ahead.
..Facing traffic
..Headlights OFF
..Emergency lights ON
YOU SHOULD BE HERE!

Key Message: Suggest patrol vehicle positioning.
Est. Presentation Time: 3-4 minutes
Explanation of Cues/Builds: Bullets appear on subsequent clicks.
Suggested Comments: This is what we recommend. Remember each case
is different and that judgment is involved. Use common sense! We
recommend FACING TRAFFIC before the 2nd and 3rd sign. This is when
motorists are about to make their maneuvers.
Suggested Questions: Why facing traffic? Advantages? Disadvantage? See
following Slide.
Additional Information: There is little information on this. This is what
one state (Louisiana) is doing. This is not required by the MUTCD or any
standard that we are aware of.
Possible Problems: This may be controversial. Be prepared to defend your
suggestion (see next Slide). Do not argue. This is a suggestion only.

Slide 97

Why Face Traffic??
..Larger field of view
..More alert!
..Engine protects you
..Not the gas tank!
..Air bags protect you
..Allows your position to be dynamic

Key Message: Discuss why we suggest to face traffic.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: These are the advantages of facing traffic. The
disadvantages would be opposite.
Suggested Questions: None
Additional Information: Pay attention to traffic!
Possible Problems: This may be against their practices. Make your point as
a recommendation and be prepared to defend it.

Slide 98
Your Position is Dynamic!
..May need to to move your vehicle often
..Minimizes crashes at the end of the queue

Key Message: Stress the importance of a dynamic position.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: If the queue builds to the point where the signs are
no longer effective, move to a location where you can reduce speeds by your
presence. This reduced speed would minimize the severity of a vehicle
impacting the end of a queue.
Suggested Questions: None
Additional Information: This highlights the importance of facing traffic:
You can see what is happening!
Possible Problems: This may be against their practices. Make your point as
a recommendation and be prepared to defend it.

Slide 99

Use of Emergency Lights
..Use emergency lights only
..Headlights off during nighttime
..May be helpful during the day

Key Message: Discuss which lights to use.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Do not use your headlights, particularly if facing
traffic at night. They blind drivers and can be distracting. Use your
emergency lights only.
Suggested Questions: What's wrong with using headlights?
Additional Information: When in the presence mode, you want to be visible
and recognized as a LEO. Your emergency lights accomplish that.
Possible Problems: Attendees may have their own policies. Encourage
discussion.

Slide 100

If Traffic Backs Up....
..Queuing beyond the advance warning signs may cause rear end crashes
..Move your vehicle back (toward traffic) to stay ahead of the traffic queue
Stay far enough ahead of stopped traffic to give fast-moving cars plenty of time to stop (approx. 1/4 mile.)

Key Message: Discuss procedures when traffic back up, beyond the advance
warning signs.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: Contractors may be encouraged to move the signs,
but it is not likely that they will do this. Your job is to keep an eye on traffic
and position yourself where you can effectively help lower speeds of
vehicles approaching the end of the queue. Use your judgment and common
sense.
Suggested Questions: Why a 1/4 mile? Refer to the discussion on PRT. 1/4
mile is 1320 feet.
Additional Information: The 1/4 mile is what the state of Louisiana
recommends.
Possible Problems: This may be against their practices. Make your point as
a recommendation and be prepared to defend it.

Slide 101

Moving Operations
..The work zone moves continuously
..Example: Striping
..May use truck-mounted attenuators
(TMA) to protect workers
..Unlike patrol vehicles, designed for impacts

Key Message: Briefly discuss moving operations.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Define moving operations as those that move
continuously. If they move intermittently, they may be referred as "mobile",
but sometimes the two are used interchangeably. The fact that the operation
is moving does not mean we do something different. As far as the motorists
are concerned, they need the same warning, guidance, control and forgiving
design. However, simplified procedures are acceptable, such as using
yellow warning lights and/or truck-mounted attenuators.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 102

Installation and Removal of Stationary Lane Closures
..Devices are installed "with the flow of traffic"
..Removed "against the flow of traffic"
..Except for detours
..Reverse the above instructions

Key Message: Briefly discuss installation and removal procedures.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: DETOUR sign appear on click.
Suggested Comments: Generally, devices are installed with the flow of
traffic and removed against the flow of traffic. This way, the AWA is
activated first and removed last, to give motorists the warning the
continuously need. Detours are done backwards and are the only exception
to the rule. By installing detours against the flow of traffic we make sure
traffic is not detoured until the detour installation is complete.
Suggested Questions: Why are detours done backwards?
Additional Information: None
Possible Problems: None

Slide 103
Not to
scale
Install
"downstream"
Remove
"upstream"
Key Message: Illustrate point made in previous Slide.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: Bottom box appears on click. Top box appears
on second click.
Suggested Comments: Define "downstream" as "with the flow of traffic"
and "upstream" as "against the flow of traffic". Repeat briefly the
information from the previous Slide.
Suggested Questions: Why is it done this way?
Additional Information: When is the arrow board removed?
Possible Problems: LEOs do not do this. So try to be as brief as possible with
this Slide.

Slide 104

Officer's Visibility
SAFE?
VISIBLE?

Key Message: Briefly discuss the importance of the officer's visibility (when
outside the patrol vehicle).
Est. Presentation Time: Less than 1 minute.
Explanation of Cues/Builds: None
Suggested Comments: The officer is visible at a short distance, but at speed,
a driver would not have enough time to react (because of PRT). How can we
enhance his visibility? Consider a retro reflective vest and apparel.
Suggested Questions: Is this officer visible? What color is the uniform? Is it
retroreflective? How visible, in feet, is he? Relate to PRT.
Additional Information: None
Possible Problems: Some may reject the idea of wearing a vest, or may say
that a vest keeps them from reaching their holster. Be prepared to defend.

Slide 105

High-Visibility Safety Apparel
..Wear if outside the patrol vehicle
..Retroreflective trim provides human form outline
..ANSI Class 2 or 3
..Specially designed to provide access to holsters

Key Message: Discuss high-visibility apparel.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: None
Suggested Comments: We recommend as a minimum, ANSI Class 2
apparel. Class 2 apparel have plenty of retro reflective area, needed when
working in close proximity to traffic. Class 3 is better but may require
retro reflective pants!
Suggested Questions: What is retro reflective? The material returns the light
to where it came from: The driver's eyes!
Additional Information: ANSI is the American National Standards
Institute. The standard is No. 107-1999 and it is required by the MUTCD (for
flagging operations).
Possible Problems: Some may reject the idea of wearing a vest, or may say
that a vest keeps them from reaching their holster. Be prepared to defend.

Slide 106

Module Recap
..Where do we find WZ standards & guidelines?
..What are the component parts of a TTC zone?
..What is a buffer space?
..Where is the patrol vehicle positioned?
..How are devices installed and removed?

Key Message: Module recap.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Ask questions to gauge understanding. Let students
answer. Add other questions as needed.
Suggested Questions: Listed on the Slide.
Additional Information: None
Possible Problems: None

Slide 107

Recommended
Practices
Session Title: Module 3. Recommended Practices
Performance-Based Learning Outcomes:
Review and summarize the practices recommended in this course
Instructional Method: Lecture
Session Time: 14 Slides. Approximately 30 minutes depending class
participation.
Evaluation Plan: The learning outcomes are evaluated at the end of each
module using the questions contained in the last Slide of that module and
through the exercises.

Slide 108

Module Objectives
..Summarize safe operating practices for LEOs working in WZ

Key Message: List module objectives.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: None
Additional Information: Consider this a review/summary of what we have
learned so far.
Possible Problems: None

Slide 109

About Recommended Practices
..Not requirements, but recommendations
..Few specific standards/guidelines exist
..None in the MUTCD
..Every case is different!
..Use your judgment!

Key Message: Frame the recommendations/practices in this course.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Many of the practices discussed in this course are
recommendations. Few standards exist and every case is different, so be
prepared to use your judgment.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 110

Recommended Practices
1. BEFORE the WZ starts
2. On ARRIVAL at the WZ
3. While at the WZ
A. Stationary operations
B. Moving operations

Key Message: List the recommended practices by the three categories
shown.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: Who remembers the difference between stationary
and moving operations?
Additional Information: None
Possible Problems: Avoid discussing these at this point. This is just a list
Slide. Each category is discussed in the following Slides.

Slide 111

1. BEFORE the WZ Starts
..Attend the pre-construction conference, if possible
..Familiarize yourself with the project
..Identify your point of contact
..WZ Supervisor
..Project Engineer
..Who is responsible for the project?

Key Message: Summarize practices BEFORE the work starts.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: What about expressing concerns for your safety?
Additional Information: Stress point made during the class. Treat this as a
review.
Possible Problems: It is not likely that LEOs would have access to the
Traffic Control Plan, so ask the POC.

Slide 112

2. On ARRIVAL at the WZ
..Be early!
..15-minute rule
..Contact your point of contact
..Identify your role and safest location
..Gather information about the project
..Drive through the WZ
..Note signs in the advance warning area
..Identify possible relocating procedures

Key Message: Summarize practices on ARRIVAL at the work site.
Est. Presentation Time: 2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Review the 15-minute rule. Stress the drive through,
in both directions. Look at signs in the AWA, anticipate congestion, and
think ahead!
Suggested Questions: What about identifying an escape route? If you are
facing traffic, leaving the vehicle is easier, since you are closer to the edge of the road.
Additional Information: None
Possible Problems: None

Slide 113

3. WHILE in the WZ
..Be alert!
..Be visible!
..Be in contact!
..If applicable, face traffic!
..Pay attention to queues that may form and relocate as necessary
..Contact your POC if adjustments are needed

Key Message: Summarize practices WHILE at the work site.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: What about if you have to leave your vehicle?
Retro reflective apparel!
Additional Information: Treat this as a review.
Possible Problems: None

Slide 114

3A. Stationary Operations
..On the shoulder
..Not in buffer space
..Relocate as needed based on traffic condition
..1/4 mile behind the end of the queue

Key Message: Discuss potential patrol vehicle position during stationary
work zones.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: What does "stationary" mean? The work zone layout
does not move, as opposed to a "moving" operation. Why 1/4 mile?
Additional Information: Treat this as a review.
Possible Problems: None

Slide 115

3B. Moving Operations
..The work zone moves continuously!
..So should you!
EXAMPLES are paving, striping, rumble strips, milling operations, etc.

Key Message: Discuss potential patrol vehicle position during moving work
zones.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: Text box appears on click.
Suggested Comments: Self-explanatory. Define "moving" as "the activity
area moves", either intermittently of continuously. Even it is moving, WZ
principles are the same!
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 116

3B. Moving Operations
..Your position will change
..May have to move in reverse on the shoulder
..This may not be feasible if moving "fast"
..REMEMBER:
..Your role is PRESENCE
..You are not a crash attenuator!

Key Message: Discuss potential patrol vehicle position during moving work
zones.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Self explanatory. "Moving fast" refers to the relative
speed between the work vehicles and traffic. Most moving operations are
moving slowly, so the speed difference is high, increasing the severity of
crashes. If moving slowly, then moving in reverse becomes feasible and
recommended. This way you will face traffic!
Suggested Questions: None
Additional Information: Treat as a review.
Possible Problems: None

Slide 117

450'
500'
1/4
mile
1/4
mile

Key Message: Reinforce the ON THE SHOLDER, FACING TRAFFIC recommendation.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None Suggested
Comments: Graphic shows the position of the vehicles during
the crash discussed during the course introduction. This was a moving
operation. The patrol vehicles did not have to be in the moving (open) lanes.
Stress the 2 things to do: 1) Be on the shoulder, not in the buffer space, and
2) Face traffic to protect yourself, move if necessary and have a larger field
of view.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 118

DO WHY?
Attend the pre-construction To familiarize yourself with the
conference and ask questions project
Discuss the TCP To understand the project
Communicate with the WZ To express concerns; to
supervisor establish a point of contact
15-minute rule Common courtesy
Position your vehicle in the To avoid parking in the taper
safest, most efficient location or buffer areas
Face forward To have a larger field of view;
better protection; dynamic

Key Message: Summarize the recommended practices discussed in this
class.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: Table appears on click.
Suggested Comments: Self-explanatory.
Suggested Questions: None
Additional Information: Treat as a review.
Possible Problems: None

Slide 119

Protect yourself!
To be visible!
if outside the vehicle
location
Be alert at all times
WHY? DO
To protect your life!
Wear retroreflective apparel
To be at the most effective Move vehicle position as
traffic conditions change
To see what's coming; to
move as needed

Key Message: Summarize the recommended practices discussed in this
class.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: Table appears on click.
Suggested Comments: Self-explanatory.
Suggested Questions: None
Additional Information: Treat as a review.
Possible Problems: None

Slide 120

Module Recap
..What are some of the recommended practices when working in a work zone?
..Before?
..During?

Key Message: Module recap.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Self-explanatory.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 121

Application Workshop
Session Title: Module 4. Application Workshop
Performance-Based Learning Outcomes:
Apply the concepts learned in this course through hands-on exercises.
Instructional Method: Workshop
Session Time: Approximately 30 minutes depending class participation.
Evaluation Plan: The learning outcomes are evaluated at the end of each
module using the questions contained in the last Slide of that module and
through the exercises.

Slide 122

Module Objectives
..Apply the concepts learned to a freeway lane closure
..Case 1. Without a back up
..Case 2. With a back up
..Discuss possible solutions, variations and adjustments

Key Message: List module objectives.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self explanatory.
Suggested Questions: None
Additional Information: Divide the class into groups of 6 maximum, 4
preferred. Hand out the exercise materials. If not available, students may
use a sheet of paper and draw as needed. There are a total of four exercises
that can be used. Introduce both of the first two cases at once and give them
time to complete. Walk around the groups and gauge their understanding
and participation. Assist as needed. Introduce the second two for discussion
purposes. All four cases can be used if needed - the instructor should tailor
this module to provide maximum effectiveness for the situation and
determine what approach would be most effective based on the make up of
the class (LEOs, DOT rep's, split, etc.)
Possible Problems: None

Slide 123

Given:
• Four-lane freeway in a
• Speed = 55 mph
• Lane width = 12 ft.

• Signs (& spacing) needed
• Length of taper & buffer
shown
• Position of patrol vehicle for
presence and enforcement
Case 1: Light Traffic
rural area, light traffic
Duration: 6 daylight hours
Indicate:
necessary to close the area
Key Message: Introduce Case 1.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: It is a 4-lane freeway. We will be addressing the
Northbound direction only. Notice the location of the work space. Place
signs, arrow panels, tapers, buffer space, etc. Be specific, noting distances
between signs, taper and buffer lengths, etc.
Additional Information: Divide the class into groups of 6 maximum, 4
preferred. Hand out the exercise materials. If not available, students may
use a sheet of paper and draw as needed. Introduce both cases at once and
give them time to complete. Walk around the groups and gauge their
understanding and participation. Assist as needed.
Solution:
L= 660'
Buffer = 495"
Signs:
A = MERGE RIGHT (1,000)
B = RIGHT LANE CLOSED (1,500')
C = ROAD WORK AHEAD (2,640')
Cones @ 55' on taper and 110' on tangent
Patrol vehicle located between the A and B signs!

Slide 124

Given:

1, except....
• Heavy traffic slowly creates a
Discuss:
• Possible adjustments
• Position of patrol vehicle
• Safest place to pull-over
Same conditions as in Case
2-mile backup from the
beginning of taper
violators
Case 2: Heavy Traffic
Key Message: Introduce Case 2.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Same as previous: It is a 4-lane freeway. We will be
addressing the Northbound direction only. Notice the location of the work
space. Place signs, arrow panels, tapers, buffer space, etc. Be specific, noting
distances between signs, taper and buffer lengths, etc.
Suggested Questions: None
Additional Information: Solution will be the same. Adjustments may
include moving the patrol vehicle. Where? Let them discuss advantages and
disadvantages and play devil's advocate.
Possible Problems: None
Solution: Same solution but patrol vehicle should be relocated to:
2 1/4 mile from beginning of taper.

Slide 125

Case 3
..Single LEO on scene. Work zone is 10 miles long on a north-
south rural, multi-lane freeway - 3 lanes each direction with
10-foot shoulders.
..A serious injury crash occurs 500 yards from an off-ramp inthe NB lanes in the middle of the project, blocking all three
lanes in that direction.
..There is a concrete median barrier. The next nearest
interchange is 5 miles on either side of this one.
..The LEO is patrolling three miles up stream from the crash.
..Contractor personnel are present in the vicinity of the crash.
The nearest town is seven miles south of the project.
Key Message: Introduce Case 3.
Est. Presentation Time: 2-3 minutes
Explanation of Cues/Builds: None
Suggested Comments: Set up #1 - Single LEO is on scene. Work zone is 10 miles long on a
north-south rural, multi-lane freeway - 3 lanes each direction with 10-foot shoulders. A
serious injury crash occurs 500 yards from an off-ramp in the NB lanes in the middle of the
project, blocking all three lanes in that direction. There is a concrete median barrier. The
next nearest interchange is 5 miles on either side of this one. The LEO is patrolling three
miles up stream from the crash. Contractor personnel are present in the vicinity of the
crash. The nearest town is seven miles south of the project.
Suggested Questions:
What is the communication sequence of events?
What part does the LEO play?
Where will the emergency vehicles be directed to go?
What information will be given to the media and by whom?
Additional Information: This case was designed to generate discussion and may depend
on other factors in the situation.
Possible Problems: None
Solution: Contractor should alert LEO of the crash - LEO would then report crash and
appropriate emergency services personnel. LEO can move downstream to locate the back
of the queue and pull over on the shoulder (possibly facing traffic to be able to move as the
queue builds). LEO should request assistance in responding to the crash so that he/she is
able to continue with work zone presence and patrol duties.

Slide 126

Case 4
..A temporary work zone, 45 MPH, four-lane city arterial.
..The work area is in the eastbound outside lane (closed).
..The taper is comprised of 12 cones spaced 10 feet apart,
and a flagger has been positioned at the beginning of the
lane taper to direct eastbound traffic
..Fifty feet ahead of the flagger is a sign reading "Be Prepared
to Stop". One-hundred-fifty feet in front of the BPTS sign is a
sign reading "Road Work Ahead".
..The LEO has just driven through the work area in advance of
positioning himself/herself for patrol.
Key Message: Introduce Case 4.
Est. Presentation Time: 2-3 minutes
Explanation of Cues/Builds: None
Suggested Comments: Set up #2 - A temporary work zone has been set up on a 45 MPH, four-lane
city arterial, two 12-foot lanes in each direction. The work area is in the lane next to the curb of the
eastbound lanes and both lanes of eastbound traffic are being reduced to one. Westbound traffic is
unaffected. The taper closing the curb lane is comprised of 12 cones spaced 10 feet apart. A flagger has
been positioned at the beginning of the lane taper to direct eastbound traffic to slow and to merge and
is standing in the middle of the lane being closed, just inside the cone taper. Fifty feet ahead of the
flagger is a sign reading "Be Prepared to Stop". One-hundred-fifty feet in front of the BPTS sign is a
sign reading "Road Work Ahead". The LEO has just driven through the work area in advance of
positioning himself/herself for patrol.
Suggested Questions:
What things would the LEO be likely to report to the work area foreman for correction?
Having reported into the foreman, the LEO patrol vehicle takes up a position to slow traffic in advance
of the work area. Where should the vehicle best be positioned?
Additional Information: This case was designed to generate discussion and may depend on other
factors in the situation.
Possible Problems: None
Solution: Minimum merging taper length should be 540 feet (currently only 110 feet given 12 cones
spaced 10 feet apart); there may not be any buffer space in the setup (should have 360 feet); signs
should be spaced 350 feet apart - on approach, begin with "Road Work Ahead" followed by sign that
shows right lane merging into left lane; a flagger is not necessary in this situation.
Don't park vehicle in buffer space or in any lanes in this situation - best position is within the signing
but it's situation specific; have to see what is available access-wise around the area (parking lots, etc.),
how close the nearest intersection is, what the street looks like upstream, etc.

Slide 127

Module Recap
..Patrol vehicle position is
..Important
..Critical
..Dynamic
..May vary depending on traffic conditions and other factors

Key Message: Module recap.
Est. Presentation Time: 1-2 minutes
Explanation of Cues/Builds: None
Suggested Comments: Self explanatory.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 128

Closing
Session Title: Module 5. Closing
Performance-Based Learning Outcomes:
Close the course
Instructional Method: Lecture
Session Time: Approximately 10 minutes depending class participation.
Evaluation Plan: Course evaluation

Slide 129

Module Objectives
..Review course objectives
..Discuss your expectations
..Complete course evaluations
..Adjourn

Key Message: List module objectives.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self explanatory.
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 130

Course Objectives
..To provide you with working knowledge of traffic control work zones
..To define your roles and responsibilities when working in work zones

Key Message: Review course objectives.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: These are the objectives we gave ourselves at the
beginning of the course. Read them. Have we met the objectives? Anyone
who feels we did not meet these objectives?
Suggested Questions: Do you have a better understanding of work zones
now? More so than 4 hours ago?
Additional Information: None
Possible Problems: None

Slide 131

You should be able to:
1. Understand standards and guidelines related to temporary traffic control in work zones
2. Understand the role of law enforcement officers in work zones

Key Message: Review things participants should be able to do AFTER
taking this course.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self explanatory
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 132

You should be able to:
3. Recognize the component parts of a typical work zone
4. Recognize proper practices and procedures related to work zones and the role of law enforcement officers

Key Message: Review things participants should be able to do AFTER
taking this course.
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self explanatory
Suggested Questions: None
Additional Information: None
Possible Problems: None

Slide 133

Your Expectations
..Did we meet your expectations?
..Did you get information you can use?
..How do you feel about work zones and workers now?

Key Message: Discuss participants expectations?
Est. Presentation Time: 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Self explanatory.
Suggested Questions: Did we meet your expectations for this class?
Additional Information: Seek class participation.
Possible Problems: If none, ask questions to gauge understanding.

Slide 134

Course Evaluations
..How can we improve the course?
..Your honest input will help us!
..Negative and/or positive

Key Message: Complete course evaluations.
Est. Presentation Time: 5 minutes
Explanation of Cues/Builds: None
Suggested Comments: Please complete the course evaluations. Be honest.
We appreciate negative and/or positive input. Your name is optional.
Suggested Questions: None
Additional Information: If multiple instructors, indicate which one is A and
which one is B.
Possible Problems: Give them sufficient time to complete.

Slide 135

THANK YOU!!
Safe and Effective Use of Law Enforcement Personnel in Work Zones

Key Message: END of course.
Est. Presentation Time: Less than 1 minute
Explanation of Cues/Builds: None
Suggested Comments: Thank you for your attendance. I enjoyed having you here. I hope you found it beneficial. Be safe!
Suggested Questions: None
Additional Information:
Possible Problems: Don't forget your laptop's power cord!

Page last modified on December 10, 2014.
Safe Roads for a Safer Future - Investment in roadway safety saves lives
Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000