U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000


Skip to content
Facebook iconYouTube iconTwitter iconFlickr iconLinkedInInstagram

Safety

FHWA Home / Safety / Roadway Departure / Pavement Friction / Pavement Friction

Case Studies and Noteworthy Practices

CASE STUDY: SOUTH CAROLINA
US 25-Greenville County

USDOT triskelion logo.
U.S. Department of Transportation
Federal Highway Administration

FHWA Office of Safety Logo: Safe Roads for a Safer Future - Investment in roadway safety saves lives.

FHWA-SA-15-056

View the PDF Version [2 MB]

A Cost-Effective and Time-Sensitive Safety Solution

Image depicts a comparison of safety on the treated road before and after, showing a 56.5 percent decrease in total crashes per year (from 9.6 before to 4.2 after) and a 68.1 percent decrease in wet crashes per year (from 8.1 before to 2.6 after). The cost benefit in terms of net annual benefit is an 80 percent savings, with the reconstruction alternative costing $5 million and the HFST application costing only $1 million. The time savings comparison shows a benefit with HFST, which takes only 6 months to implement, versus the reconstruction alternative, which was estimated to take more than 3 years for design and construction.

Map of the one-mile section of Greenville US 25 treated with HFST. Copyright Google Maps.

A one-mile section of US 25 in Greenville County had been a cause for concern for the South Carolina Department of Transportation (SCDOT) for many years. Located in rural, mountainous terrain, and often subject to inclement weather including rain, snow, ice, and fog, US 25 carries traffic on two lanes in each direction and is separated only by a damaged and brittle concrete barrier. US 25 changes dramatically, from a relatively straight road in North Carolina directly to this particular section in South Carolina with horizontal and vertical curves and a 6 percent grade. US 25 has a speed limit of 55 mph and carries approximately 10,000 vehicles per day with heavy truck traffic.

SCDOT discovered a number of factors contributing to the high crash rates along this short section of US 25. One significant factor was that the concrete barrier's design did not allow for proper drainage, channeling water to the driving lane and shoulder. Speeding, inadequate pavement superelevation, and sight distance constraints also contributed to the safety issues at this location.

In 2000, SCDOT considered funding a major reconstruction project which involved replacing and updating the barrier wall and modifying the roadway's superelevation and drainage structures. However, with the project's estimate coming in at nearly $5 million, this project was unlikely to happen. Both costly and lengthy, the overall project development timeline for this alternative would have spanned approximately three years, and would have involved an extensive work zone and detour which would have inconvenienced local residents and drivers traveling through this area.

Over the years, low-cost measures of additional signing and markings were added along US 25, but these did not adequately address the excessive speeds and drainage issues, and the resulting safety improvement was minimal at best. At one point, a dynamic message sign (DMS) was installed to display a regulatory 45 mph speed limit during rainy conditions. However, due to the rural nature of this road segment and the wide road template, speeds remained excessive.

Before and after photos of the treated roadway.

In 2008, a High Friction Surface Treatment (HFST) was applied to this curvy stretch of US 25. SCDOT had used this pavement treatment on ramp segments to increase skid resistance in locations where friction demand was high, but this one-mile project was the largest application to date, and at the time, it was unclear whether HFST would mitigate the hydraulic issues drivers experienced on this segment. With the planning process and installation complete in approximately six months, the HFST project cost SCDOT $1 million, which was 80 percent less than the previously considered reconstruction project.

A before and after study evaluating the HFST project's success on US 25 revealed significant safety benefits, with a 68 percent reduction in wet crashes and a 56 percent reduction in total crashes. Six years after HFST installation, SCDOT reports the pavement treatment is holding up very well, considering the high exposure to snow plowing.

To develop its current HFST specification, SCDOT used the AASHTO specification as the base model and integrated pieces from other States' specifications as well as their own experiences with the treatment. While their HFST specification is still evolving, SCDOT believes it strikes a good balance between quality materials and application, while still maintaining reasonable contractor expectations and competitive bidding.

Citing a before and after study of seven HFST project locations, SCDOT experienced an 81 percent reduction in wet crashes and 71 percent reduction in total crashes. Since HFST has proven to be a very cost-effective safety countermeasure, SCDOT has installed 20 HFST projects, with approximately 20 more locations planned for 2015. Widespread deployment will be incorporated once the DOT identifies the horizontal curves throughout the State. The benefit/cost analysis for these locations has proven HFST to be a very cost-effective countermeasure.

For more information:

Joseph Cheung
FHWA Office of Safety
joseph.cheung@dot.gov
Frank Julian
FHWA Resource Center
frank.julian@dot.gov
Joey Riddle, Safety Engineer
South Carolina DOT
RiddleJD@scdot.gov

Return to top

Page last modified on June 17, 2015
Safe Roads for a Safer Future - Investment in roadway safety saves lives
Federal Highway Administration | 1200 New Jersey Avenue, SE | Washington, DC 20590 | 202-366-4000